09-015CITY OF S E O RESOLUTION NO. 09-015 A SOLUTION APPROVING CHANGE ORDER 1 FOR THE S.E. AREA WATER TOWER REHABILITATION PROJECT AND ACCEPTING FINAL IMPROVEMENTS CITY PROJECT NO. 05-04 WHEREAS, on September 22, 2008 the City of Shorewood entered into a contract for construction with Classic Protective Coatings, Inc, for the S.E. Area Water Tower Rehabilitation Project, City Project No. 05-04; and WHEREAS, Change Order 1 has been prepared and is attached as Exhibit A, for additional work outside of the original contract; and WHEREAS, the Director of Public Works has reviewed said Change Order and found it to be cost effective for the project; and WHEREAS, KLM Engineering and the Director of Public Works has inspected the work completed under said contract and has found that the work has been completed according to the plans and specifications; and WHEREAS, the Contractor has petitioned the City to accept the final improvements for the project. NOW, THEREFORE BE IT RESOLVED by the City of Shorewood: 1. Change Order Number 1 is hereby approved with Classic Protective Coatings, Inc., that incorporates services outlined in Change Order 1, attached hereto as Exhibit A. 2. The City does hereby accept the work completed pursuant to said contract and authorizes final payment to the Contractor, subject to the following items: a. The Contractor must make satisfactory showing that he has complied with the provisions of Minnesota Statutes 290.92 requiring withholding of State Income Tax. b. Evidence in the form of an affidavit that all claims against the Contractor by reasons of the contract have been fully paid or satisfactorily secured. ADOPTED by the City Council of the City of Shorewood this 9th day of March 2009. ATTEST: Christine Lizee, Mayor for/Clerk e r 1'_r1V -lip { ;;755 C JfJIFiY CLl ~t~l~JD, MfP..ESOTA 553318927 e(952) 474 3236 FAX (952) 474-0128 ® www.ci.shorewood.mn.us cityhall@ci.shorewood.mn.us City of Shorewood Change Order Request Form PROJECT: S.E. Area Water Tower Rehabilitation Project CITY PROJECT NO: 05-04 GENERAL CONTRACTOR: Classic Protective Coatings, Inc. DATE OF ORIGINAL AWARD OF CONTRACT: September 22, 2008 CHANGE ORDER REQUEST NO.: 1 Original Contract Amount: Total Amount of Change Order Requested: (as Documented as Attachment 1) Total Amount of Previous Change Orders: Revised Contract Amount: $ 378,000.00 $ 4,951.13 $ 0.00 $ 382,951.13 I hereby acknowledge that the Change Order No. 1, as represented above has been considered and approved by the Sh rewood~Aity Council on March 9, 2009. i the - Curia r izee Mayor Date 0 c," Date: Exhibit A PRINTED ON RECYCLED PAPER f 4.0 4"" March 1 , 2009 City of Shorewood, MN Mr. Larry Brown 5755 Country Club Road Shorewood, MN 55331 Re: Closeout Prices for the Propane Heat for the City project 05-04 Larry: I have itemized the expense list for your reference. 1. Propane Fuel Tank Set. Price-$105.00 2. Propane Fuel Consumption at 350.00 Per Day for 7 Days. Price -$4,230.52 3. Rental of two 400,000 BTU Heaters Per Day. Price -$465.61 4. Ducting and Fittings. Price - $150.00 Total: $4,951.13 Please let me know if you have any questions. Sincerely, Classic Protective Coatings, Inc. John Newkirk N7670 State Highway 251 Menomonie Wisconsin 54751-5928 SSPC Telephone 715-233-6267 Facsimile 715-233-6268 SSPC QPI QP2 www.classicprotectivecoatings.com Attachment 1 Wisconsin Texas ( Florida