09-016CITY OF S O E O
RESOLUTION NO. 9-016
A SOLUTION APPROVING A CHANGE ORDER 3
FOR THE RADIO READ WATER METER PROJECT,
CITY PROJECT NO. 07-04
WHEREAS, on May 29, 2007, the City of Shorewood entered into a contract for
construction with Northern Water Works Supply for the Radio Read Meter, Software Installation
and Appurtenances Project, City Project No. 07-04; and
WHEREAS, the City Engineer has prepared Change Order 3, attached hereto as Exhibit
A, for revisions to the original contract; and
WHEREAS, the City Council has reviewed said Change Order and found it to be cost
effective for the project.
NOW, THEREFORE BE IT RESOLVED by the City of Shorewood to approve
Change Order Number 3 with Northern Water Works Supply, that incorporates services outlined
in Change Order 3, attached hereto as Exhibit A.
ADOPTED by the City Council of the City of Shorewood this 23rd day of March, 2009.
ATTEST:
LLL: L --1
Christine Liz6e, Mayor
RADIO READ WATER METER PROJECT
CITY PROJECT NO. 07-04
CITY OF SHOREWOOD
3119109
OWNER:
CONTRACTOR:
CITY OF SHOREWOOD
NORTHERN WATER WORKS SUPPLY
5755 COUNTRY CLUB RD
1694 91ST AVE NE
SHOREWOOD, MN 55331
BLAINE, MN 55449
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
Increase the quantity of installed 5/8" x 3/4" Neptune E-Coder R900i water meters to
approximatley 307 meters, in addition to previous change orders.
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, S
HAPE, OR
FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE: $255,295.38
ORIGINAL CONTRACT TIME:
12/30/2007
PREVIOUS CHANGE ORDERS: $31,730.17
NET CHANGE FROM PREVIOUS CHANGE ORDERS:
NONE
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER: $287,025.55
CONTRACT TIME PRIOR TO THIS CHANGE ORDER:
12/30/2007
NET INCREASE/DECREASE OF THIS CHANGE ORDER: $90,500.00
NET INCREASE OF CHANGE ORDER:
12/15/2009
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS: $377,525.55
CONTRACT TIME WITH APPROVED CHANGE ORDERS
12/15/2009
RECOMMENDED BY:
APPROVED BY:
JAMES LANDINI, PE, CITY ENGINEER
CONTRACTOR SIGNATURE
DATE
CONTRACTOR
APPROVED BY:
MAYOR CHRIS LIZEE
CITY ADMINISTRATOR
DATE
DATE
CADocuments and SettingsljeanlLocal SettingslTemporary Internet FileslOLKMCopy of Change Order 3CO 1