11-13-12 Council Mtg Item 9A-LRT Trail Crossing Feasibility StudyThreeRivers
PARK DISTRICT
DRAFT
t .
h_
Y
:� a - :,. �: ♦♦ ,
M
J
L ,
Ar x.
lt k.�
i / 4
a,
FEASIBILITY REPORT FOR
Lake Minnetonka LRT Regional Trail &
CSAH 19 (Manitou Road) Grade Separated Trail
Crossing
Three Rivers Park District
September, 2012
I hereby certify that this plan, specification, or report was prepared by me or under my direct
supervision and that I am a duly Licensed Professional Engineer under the laws of the State of
Minnesota.
Casey E. Black, P.E.
Date: September 7, 2012
Reg. No. 49163
Table of Contents
ExecutiveSummary ......................................................................... ............................... 1
Introduction...................................................................................... ............................... 3
StudyObjectives ................................................................................ ..............................4
Crossing Location /Trail Connections ............................................. ............................... 4
PropertyIdentification .................................................................... ............................... 5
ExistingUtility Impacts ..................................................................... ..............................6
TrailCrossing Options ...................................................................... ............................... 7
StructureType .................................................................................. ............................... 10
BridgeAesthetics ............................................................................... .............................11
Property Easements and Acquisitions .......................................... ............................... 11
ProjectCosts ....................................................................................... .............................12
Property Easement and Acquisition Costs ...................................... .............................13
Summary and Recommendations ................................................. ............................... 14
Schedule ........................................................................................... ............................... 15
Appendix .............................................................................................. .............................16
A Site Photos
B Approach & Crossing Profiles
C Trail Crossing at CSAH 19 (Manitou Road) Alignments
D Structure Type Cross Sections & Examples
E Trail Bridge Concepts
F Existing Site Topography, Utility Considerations & Property Identification
G Trail Crossing Cost Estimate Matrix
H Trail Crossing Recommendations
I Planning Milestones & Project Schedule
Executive Summary
This report assesses the feasibility of constructing a grade separated trail crossing at the
intersection of the Lake Minnetonka LRT Regional Trail (LMLRT Regional Trail) and CSAH 19
(Manitou Road) in the cities of Tonka Bay and Shorewood, MN. The intent of this grade
separated trail crossing is to provide uninterrupted connection to the LMLRT Regional Trail,
recreational facilities, surrounding residential neighborhoods, and provide a safer pedestrian
alternative to the at -grade crossing at CSAH 19 (Manitou Road) that exists today.
CSAH 19 (Manitou Road) is a two -lane road that serves as a main north -south corridor through
a large residential area surrounding multiple bays of Lake Minnetonka, and is part of the county
state aid transportation system. CSAH 19 (Manitou Road) is generally characterized by
relatively large suburban and lakeshore residential developments with small commercial
properties at some of the larger intersections.
In recent years, safety of the at -grade trail crossing at the intersection of the LMLRT Regional
Trail and CSAH 19 (Manitou Road) has been improved by separating the northbound and
southbound lanes with a center median. The median has an at -grade crossing for the trail, and
provides a safe zone for pedestrians crossing both lanes of traffic. Viable options to further
improve safety for the LMLRT Regional Trail crossing were reviewed and a grade separated trail
crossing of LMLRT Regional Trail and CSAH 19 (Manitou Road) in the vicinity of the existing
intersection has been proposed. This proposed grade separated crossing would provide a safe
and convenient crossing of CSAH 19 (Manitou Road) for the local residents and trail users.
The trail crossing can be constructed using a variety of structure types. An example of each
structure type and a representative project is presented in Appendix D. While this report
evaluated both bridge and tunnel options, it is recommended that a bridge be considered as
the preferred option. Tunnels are generally used in areas that are more open and less dense.
In developed areas, tunnels tend to be less aesthetically pleasing. They also can become
havens for nuisance activities. While typical tunnel costs may be less than a bridge, there could
be substantial utility relocation costs added to this project due to the possibility of large
numbers of public and private utilities below the street. There could also be substantial costs
associated with groundwater and the construction and maintenance of a structure that exists
below the water level of Lake Minnetonka.
We recommend that the location of the trail bridge be centered in the HCRRA ROW as
indicated in Option 1 (noted in this report as "Preferred Option 1 "), and that a prefabricated
steel truss be used as the main span of the bridge crossing. The use of a steel truss eliminates
the need for a center pier in the existing median, while also providing a long enough main span
Page 1 of 16
to allow for future expansion considerations for CSAH 19 (Manitou Road). This option also
provides for wide open sight lines rather than visual obstructions near the sides of the roadway.
A prefabricated steel truss also has the ability to be relocated for future alignment changes if
the future Light Rail Transit (LRT) corridor is designed as a shared corridor with the LMLRT
Regional Trail. In addition, this structure type tends to be more flexible for aesthetic
considerations as well. This study does not consider all main span aesthetic treatment
possibilities such as signage, logos, or lighting, but does allow for future considerations if
desired by the owner or local stakeholders.
We further recommend the approach ramps be constructed of retaining walls for a length that
provides between 5 to 6 feet of clearance to the low structure member for safety and
maintenance considerations. Approach spans should be constructed with prestressed concrete
beams for their low maintenance advantage over steel girders, and the low visibility of the
approach spans from CSAH 19 (Manitou Road).
This study does outline the possibility of using temporary trail connections for purposes of
detouring trail users during construction as permanent local access points to the LMLRT
Regional Trail. However, we recommend this decision be made by the owner with stakeholder
and community input as its value to the trail and local neighborhoods should be a point of
discussion.
A preliminary cost estimate has been prepared with consideration given to project design and
construction costs and property easement and acquisition requirements. The preliminary
estimate identifies total project and right of way costs for the trail crossing that range from $2.8
to $3.1 million in 2012 dollars. For budgeting purposes, utility relocations have been included
in the estimated project cost. However relocation costs might not become project costs, but
rather utility owner costs as they are within public Right -of -Ways and could be requested to
relocate by Hennepin County on behalf of the project.
Three Rivers Park District has identified and secured Federal funding to significantly improve
safety and the trail user experience by providing a safe pedestrian crossing that is both
functional and can provide a distinctive landmark for the community. The LMLRT Regional Trail
grade separated trail crossing should consider the need of the user, local stakeholder input, and
long -term future planning of the region and trail /LRT corridor.
Page 2 of 16
For Three Rivers Park District
In the Cities of Tonka Bay & Shorewood, MN
CSAH 19 (Manitou Road) — Grade Separated Trail Crossing
Feasibility Study
September, 2012
Introduction
CSAH 19 (Manitou Road) is a two -lane roadway that serves as a main north -south corridor
through a large residential area in the heart of the Lake Minnetonka area. CSAH 19 (Manitou
Road) is part of the county state aid transportation system. This corridor is generally
characterized by suburban and lakeshore residential developments with small commercial
properties at some of the larger intersections. The CSAH 19 (Manitou Road) corridor is a two -
lane road with shoulders. No pedestrian areas such as sidewalks or bike trails run along this
corridor.
- � >��� ♦ it r �' _` � -
L4
..
ro
k
0,
}
r4 -..� r 4
i
i__ 4 -•
Ls T
In an effort to provide the greatest pedestrian safety at the LMLRT Regional Trail intersection
with CSAH 19 (Manitou Road) the feasibility of constructing a grade separated pedestrian
crossing at this intersection has been evaluated. The grade separated trail crossing is the focus
of this feasibility study.
Page 3 of 16
The intent of this grade separated trail crossing at CSAH 19 (Manitou Road) is to provide a safer
pedestrian crossing than exists today as well as local access to:
■ LMLRT Regional Trail. The structure and trail must comply with the Americans with
Disabilities Act (ADA).
Recreational facilities. The crossing will provide local residents safe access to Manitou
Park north of the LMLRT Regional Trail and west of CSAH 19 (Manitou Road).
■ Adjacent residential neighborhoods.
Study Objectives
A grade separated trail crossing over CSAH 19 (Manitou Road) would provide pedestrians and
bicyclists an alternative to the at -grade crossing that exists today. The purpose of this study is
to:
• Identify potential locations for a new grade separated trail crossing of CSAH 19 (Manitou
Road) for the existing trail corridor.
• Conduct conceptual analysis of alignments and profiles for consideration
• Identify impacts to properties adjacent to the trail crossing and potential right of way
easements and acquisitions
• Identify impacts to existing utilities
• Outline potential structure types and aesthetic options
• Provide cost estimate of the proposed improvements
• Provide a schedule of tasks moving forward in compliance with funding requirements
Crossing Location /Trail Connections
Although some local pedestrian traffic will use the bridge as a means to bypass the at -grade
crossing, the anticipated primary users of the crossing will be recreational trail users. The
existing LMLRT Regional Trail alignment includes an at -grade crossing of CSAH 19 (Manitou
Road). The intent is to replace the at -grade crossing with a grade separated trail crossing while
utilizing the same LMLRT Regional Trail corridor. Slight trail alignment modifications may be
necessary to best fit a crossing within the existing trail corridor.
No sidewalks or trails run along CSAH 19 (Manitou Road). Due to this, there is little reason to
provide primary connections from the grade separated crossing back to the CSAH 19 (Manitou
Road) ROW. This provides the opportunity for long straight approaches to be utilized to the
benefit of trail users rather than requiring tight curved alignments, switchbacks, or helix type
approaches which typically require design exceptions.
The LMLRT Regional Trail is within the Right -of -Way (ROW) of the Hennepin County Regional
Rail Authority ( HCRRA). An agreement between Three Rivers Park District (TRPD) and the
HCRRA currently allows TRPD to use the corridor for pedestrian and trail purposes. The HCRRA
acquired the corridor for Light Rail Transit (LRT) expansion, and has the authority to reclaim the
ROW as necessary to construct the LRT system in the future.
Page 4 of 16
Discussions with HCRRA have indicated that it is possible for both the trail and LRT to exist
within the same corridor, although the existing trail alignment would need to be shifted to
accommodate both. This study considered both a trail bridge alignment that would
accommodate the future LRT corridor allowing the bridge to remain during LRT construction,
and an alignment that would be in conflict with the future LRT.
Constructing a grade separated trail crossing that is in conflict with a future LRT alignment is
not a disadvantage due to the relatively insignificant cost of the trail crossing compared to the
extensive cost of the LRT project and the long range implementation of such a project. A new
trail crossing could be constructed as a part of the LRT project.
Construction of the trail crossing will interfere with the existing trail such that users will need a
temporary detour to by -pass construction. On the east side of CSAH 19 (Manitou Road), trail
users could be routed to a temporary connection between the LMLRT Regional Trail and
Brentwood Avenue to the north by way of a trail connection at Bay Street. Local residents have
established a path through the undeveloped public ROW at this location to access the trail. On
the west side of CSAH 19 (Manitou Road), trail users could be routed to a temporary connection
between the LMLRT Regional Trail and CSAH 19 (Manitou Road) through Manitou Park. At both
locations, temporary trails would need to be constructed.
As an alternative to being used only as temporary detours for the LMLRT Regional Trail during
construction, these access points could be constructed to remain as permanent connections to
provide access points between the LMLRT Regional Trail, park users, and local residents.
Property Identification
Properties included within and adjacent to the project area which may be directly or indirectly
impacted by the construction of the crossing and temporary facilities were identified. The
impacted parcels within the vicinity of the project are listed below:
Property ID No.
Owner
Address
Type
4901 Manitou Road
2811723430047
City of Tonka Bay
Torrens
Tonka Bay MN 55331
15 Brentwood Avenue
3311723110018
J & L Development
Torrens
Tonka Bay MN 55331
NSP — Property Tax Dept
3311723110045
Northern States Power Co.
414 Nicollet Mall
Torrens
Minneapolis MN 55401
85 Brentwood Avenue
3311723110064
Dorothy Jean Tisdale
Abstract
Tonka Bay MN 55331
Hanus Enterprises
3311723110075
Fred Hanus Et Al
15801 West Oaks Drive
Torrens
Minnetonka MN 55345
15 Brentwood Avenue
3311723120001
J & L Development
Abstract
Tonka Bay MN 55331
Page 5 of 16
Refer to Appendix F for a map detailing property identification numbers for each parcel listed in
the table above.
Existing Utility Impacts
A preliminary investigation into existing utilities has been completed. Continuation of this utility
investigation will be required in the preliminary design phase of the project as potential impacts
become better defined. The options presented in this report will require varying amounts of
adjustment /relocation of the utilities for the design and construction of a pedestrian facility.
Utilities included within the project area were contacted through Gopher State One Call
(GSOC). Requests for as -built plans, maps, and field locates were made on call ticket number
121012872. Utility companies contacted by GSOC include:
• Access Communication Technologies
• City of Shorewood
• City of Tonka Bay
• Hennepin County Public Works
• Metro Waste Commission
• Centerpoint Energy
• Mediacom
• Centurylink
• Xcel Energy
Page 6 of 16
Hennepin County Regional
Rail Authority
3311723120019
Hennepin Forfeited Land
7014 Avenue South
Abstract
Suite 400
Minneapolis MN 55415
Metropolitan Council
Environmental Services
3311723120045
Metropolitan Sewer Board
Torrens
390 Robert Street North
St. Paul MN 55101
15 Brentwood Avenue
3311723120046
J & L Development
Torrens
Tonka Bay MN 55331
Village of Tonka Bay
3311723120049
Village of Tonka Bay
4901 Manitou Road
Abstract
Tonka Bay MN 55331
JR Mega Inc.
3311723120050
JR Mega Inc.
2908 Hayes Drive
Torrens
Burnsville MN 55337
Gideon's Woods Twin
Gideon's Woods Twin
Home Association Inc.
3311723120076
Abstract
Home Association Inc.
5535 Gideons Lane
Shorewood MN 55331
NSP — Property Tax Dept
3311723120080
Northern States Power Co.
414 Nicollet Mall
Abstract
Minneapolis MN 55401
Refer to Appendix F for a map detailing property identification numbers for each parcel listed in
the table above.
Existing Utility Impacts
A preliminary investigation into existing utilities has been completed. Continuation of this utility
investigation will be required in the preliminary design phase of the project as potential impacts
become better defined. The options presented in this report will require varying amounts of
adjustment /relocation of the utilities for the design and construction of a pedestrian facility.
Utilities included within the project area were contacted through Gopher State One Call
(GSOC). Requests for as -built plans, maps, and field locates were made on call ticket number
121012872. Utility companies contacted by GSOC include:
• Access Communication Technologies
• City of Shorewood
• City of Tonka Bay
• Hennepin County Public Works
• Metro Waste Commission
• Centerpoint Energy
• Mediacom
• Centurylink
• Xcel Energy
Page 6 of 16
The Trail Bridge options indicated in Preferred Option 1 and Option 2 impact utilities
suspended from the overhead power poles running parallel to CSAH 19 (Manitou Road) along
the east shoulder. Affected utilities include:
• Xcel Energy distribution lines
• MediaCom cable line and fiber optic lines
These utilities would need to be relocated to allow for a bridge crossing. It is anticipated that
the clearance to the low structural member of the bridge from the roadway will be 17' -6" from
the roadway. The structure depth in Preferred Option 1 ranges from 7' -0" to about 13' -6"
(from bottom chord to top of metal railing or top chord) resulting in an approximate maximum
structure height of 31' -0" from existing grade. Typical utility clearances to structures would
need to be observed if relocation was to include taller overhead poles rather than a buried
utility condition.
The Trail Tunnel option indicated in Option 3 would impact multiple public and private utilities.
These include:
• local sanitary sewer connections to the Metropolitan Council 30" sanitary sewer system
• local storm sewers
• gas line
• watermain
• telephone
• fiber optic line
• an open cut for tunnel installation would likely impact the adjacent overhead power
poles as well
In addition, the bottom of the excavation for installation of the tunnel as well as the elevation
of the permanent trail floor within the tunnel will be below the water level of Lake Minnetonka.
Special consideration will be necessary for the design and maintenance of a structure for this
condition as well as how to treat additional drainage. It is primarily for this reason and for
potential buried utility conflicts, a tunnel option is not recommended for this project.
Refer to Appendix F for utilities marked and surveyed in the field. Soil borings were not
obtained for this report as these are generally done as part of the preliminary engineering
design phase.
An additional Gopher State One Call request was made related to ticket number 122150491.
This ticket was a request for a field meeting that was held on August 23 2012 to discuss
concerns with impacted utilities. Meeting minutes and notes can be found in Appendix F.
Trail Crossing Options
One of the key criteria for the project is to comply with the current Americans with Disabilities
Act (ADA), International Building Code (IBC), and Minnesota Department of Transportation
(MNDOT) Bikeway Facilities Manual design requirements. Current IBC code allows for designed
Page 7 of 16
grades to be set at a maximum 5% slope without requiring the use of landings based on ADA
criteria. The IBC also allows grades up to 8.33% with the use of landings after every 2.5 feet of
vertical rise. The use of a maximum 5% slope without landings is preferred to provide a smooth
ride for trail users, and was the basis for this study. The MnDOT LRFD Bridge Design Manual
requires that the vertical clearance between the lowest structural member of the bridge and
CSAH 19 (Manitou Road) be a minimum of 17 feet 4 inches. This study used a clearance height
17 feet 6 inches to determine the bridge elevation from which the length of bridge and
approach could be estimated. This provides for possible grade changes in the future for CSAH
19 (Manitou Road).
For similar reasons, the tunnel option was also evaluated with a 5% slope at the approaches.
This was done to provide a smooth ride for trail users, and still achieve adequate cover
between the surface of CSAH 19 (Manitou Road) and the top of the tunnel. A minimum vertical
clearance in the tunnel of 10 feet was designed to comply with requirements of the MnDOT
Bikeway Facilities Manual. Appendix B contains a schematic of the assumed bridge and tunnel
profiles used to develop the crossing options.
Alignments were investigated to best serve the users and fit within site constraints. The MnDOT
Bikeway Facility Design Manual requires a minimum 90 -foot radius of curvature be used to
accommodate the desired 20 mph design speed for bicyclists. Construction of a helix or curved
switchback at the approaches is typically not feasible based on this constraint without requiring
a design exception, or substantial structural footprint. The tight constraints of the existing trail
corridor are best suited for long, straight approach configurations. Site photos are presented in
Appendix A.
Appendix C contains graphics for three grade separated crossing concepts at the intersection of
the LMLRT Regional Trail and CSAH 19 (Manitou Road), along with a comparison matrix. In
general, options indicating a trail bridge crossing could be constructed as a tunnel with
moderate adjustments to the approach configurations and additional temporary easement for
structure excavation.
The existing LMLRT Regional Trail corridor to either side of CSAH 19 (Manitou Road) best
accommodates a long straight approach to the grade separated crossing. No sidewalks or trails
exist along CSAH 19 (Manitou Road) that would require a more direct connection from the
bridge to the roadway.
The options for a trail crossing and some of their considerations are as follows:
PREFERRED OPTION 1- Trail Bridge over CSAH 19 (Manitou Road) - Centered Alignment
a. Provides an alignment near the center of the existing LMLRT Regional Trail
corridor. Does not provide for future LRT considerations.
b. Straight approach configurations at both the east and west approaches.
c. Provides temporary /permanent local connection point through public park space
to CSAH 19 (Manitou Road) at the west approach.
Page 8 of 16
d. Provides temporary /permanent local connection point at Bay Street to
Brentwood Avenue at the east approach.
e. Maximum profile grade of 5%
f. No design exceptions anticipated.
g. Temporary easements necessary for LMLRT Regional Trail detour (permanent
easements necessary for permanent local connections)
h. No temporary easements necessary for structure excavations
i. Short closure of CSAH 19 (Manitou Road) to set main span superstructure
2. OPTION 2 - Trail Bridge over CSAH 19 (Manitou Road) - Offset Alignment
a. Provides an alignment near the north edge of the existing LMLRT Regional Trail
corridor. Considers future LRT expansion.
b. Straight approach configurations at both the east and west approaches.
c. Provides temporary /permanent local connection point through public park space
to CSAH 19 (Manitou Road) at the west approach.
d. Provides temporary /permanent local connection point at Bay Street to
Brentwood Avenue at the east approach.
e. Maximum profile grade of 5%
f. No design exceptions anticipated.
g. Temporary easements necessary for LMLRT Regional Trail detour (permanent
easements necessary for permanent local connections)
h. Temporary easements necessary for structure excavation along north ROW
i. Short closure of CSAH 19 (Manitou Road) to set main span superstructure
3. OPTION 3 - Trail Tunnel under CSAH 19 (Manitou Road) - Centered Alignment
a. Provides an alignment near the center of the existing LMLRT Regional Trail
corridor. Does not provide for future LRT considerations.
b. Straight approach configurations at both the east and west approaches.
c. Provides temporary /permanent local connection point through public park space
to CSAH 19 (Manitou Road) at the west approach.
d. Provides temporary /permanent local connection point at Bay Street to
Brentwood Avenue at the east approach.
e. Maximum profile grade of 5%
f. No design exceptions anticipated.
g. Temporary easements necessary for LMLRT Regional Trail detour (permanent
easements necessary for permanent local connections)
h. Temporary easements necessary for structure excavation along north and south
ROW to accommodate a wide open cut for tunnel construction
i. Possible impacts with buried utilities in CSAH 19 (Manitou Road) ROW
j. Requires water management system for groundwater considerations due to
existing water level of Lake Minnetonka above the elevation of the bottom of
the tunnel.
k. Closure of CSAH 19 (Manitou Road) to vehicular traffic for duration of tunnel
installation.
Page 9 of 16
I. Creates areas not easily visible from public spaces which are a safety concern.
Structure Type
There are multiple structure types that could accommodate a grade separated trail crossing.
Ease of construction, site constraints, and desired aesthetics are among the key elements when
considering an appropriate structure type.
It is our opinion that four of the five structure types listed below are feasible for the CSAH 19
(Manitou Road) crossing:
• Prefabricated Steel Truss Bridge
• Steel Girder Bridge
• Prestressed Concrete Through Girder Bridge
• Prestressed Concrete Girder Bridge
■ Precast Concrete Box Culvert Tunnel (NOT RECOMMENDED)
The structure types listed for the bridge options would apply to the main span over CSAH 19
(Manitou Road), which is the visual focal point of the structure. Appendix D contains a typical
cross section of each structure type, along with examples of bridges or tunnels where these
structure types were used.
Depending on which main span option is chosen, the approach spans could be another
structure type. Approach span structure types such as formed concrete tee beams, prestressed
concrete beams, or steel girders may be considered, but final decision may be driven by cost
and aesthetic considerations to best fit the main span structure type. Parallel retaining walls
would also be used at the lower profile elevation of the approaches until between 5 to 6 feet of
vertical clearance is available from ground to the low structure member. This reduces overhead
obstructions and provides accessible maintenance areas below the approach spans.
The prestressed concrete girder with a concrete deck found on page 5 of 6 in Appendix D would
require a greater structure depth than the other bridge alternatives. To maintain adequate
vertical clearance over the roadway, the increased depth associated with this alternative
creates a need for longer bridge approaches to achieve the higher deck elevations.
The prefabricated steel truss, steel girder, and prestressed concrete through girder would all
provide a shallower structure depth to better accommodate the site constraints. While all are
viable alternatives and relatively similar in cost, each provides a different look. Further
discussion on the aesthetic aspects of the structure type is in the following section.
The precast box culvert tunnel alternative can be found in Figure 6 of 6 in Appendix D. This
option is not recommended due to traffic impacts during construction, safety concerns,
possible utility adjustments beneath CSAH 19 (Manitou Road), and construction and
maintenance concerns due to required construction below the water level of Lake Minnetonka.
A long enclosed tunnel would need additional lighting requirements for safety, and have very
little visibility from CSAH 19 (Manitou Road) or adjacent properties.
Page 10 of 16
Bridge Aesthetics
Crossing CSAH 19 (Manitou Road), the proposed pedestrian bridge will be a prominent civic
design feature that could influence the overall character of the corridor and surrounding
neighborhoods. The initial sketch options for the aesthetic character of the bridge strive to
create a structure that fits sensitively within its surroundings while also complementing the
distinct architectural identity established by Three Rivers Park District along other regional trail
corridors in the area. The primary bridge features that influence the appearance are the span
types, pier supports, retaining walls, railings, and any potential lighting. As part of this report,
two concepts illustrating different bridge structural types (truss or girder) are presented for
initial consideration.
• Steel Truss Bridge Concept— Refer to Appendix E, Figure 1 of 2
• Girder Bridge Concept - Refer to Appendix E, Figure 2 of 2
The concept sketches illustrate two unique approaches intended to facilitate further discussion
and consideration of the desired structural type and other aesthetic aspects of the bridge and
immediate surroundings.
The truss bridge type would have the signature arched "bowstring" shape with a clear span
over the roadway. The girder bridge type would have a railing that steps up in height over the
roadway and could include a center pier in the median. The proposed color finishes are light
tan on smooth concrete surfaces and reddish -brown on the steel features similar to other
Three Rivers Park District bridges in the west metro area. Additionally, a field stone formliner
texture and color is proposed for the bases of piers and retaining wall surfaces. The distinct
Park District emblem is proposed to be mounted on both sides of the bridge at the center of
the main span.
Undoubtedly, local stakeholders and the greater community will have an interest in the visual
quality of the structure. Further input from stakeholders will help ensure that it will be an
attractive and distinctive civic landmark that reflects community values.
Property Easements and Acquisitions
The proposed project will require temporary easements through public right of way to provide
a trail detour around the proposed construction. Impacted public land that exists in the study
area consists of right of way for CSAH 19 (Manitou Road) and adjoining local streets, and
Manitou Park land on the west side of CSAH 19 (Manitou Road). If Three Rivers Park District or
local agencies determine that the proposed temporary detour facilities are desirable as local
connections to the LMLRT Regional Trail, permanent easements may be required. No private
land impacts or permanent land acquisitions are anticipated to provide temporary or
permanent LMLRT Regional Trail access for this project.
Page 11 of 16
Public ROW impacts to the west of CSAH 19 include a temporary or permanent easement
through Manitou Park. Impacts include clearing brush and constructing an on grade local trail
connection between the existing LMLRT Regional Trail to the west end of the project through
the park land to either the existing parking lot, or directly to the CSAH 19 ROW and shoulder at
the southbound lane. To connect the LMLRT Regional Trail to the temporary trail through the
park, a crossing over the drainage area that runs parallel to trail along the north side will be
required. This could either be accomplished with a fill section and drain pipe to provide for
continued drainage to the west, or a small temporary bridge structure could be constructed
over the drainage ditch.
Public ROW impacts to the east of CSAH 19 include a temporary or permanent easement
through the public land at Bay Street. Impacts include clearing brush and constructing an on
grade trail connection between the existing LMLRT Regional Trail to the east end of the project
through the public land to a connection at Brentwood Avenue. Local residents have already
worn a foot path to access the trail at this location.
The proposed project may require temporary easements impacting private lands depending on
the crossing option selected. Temporary easements would be necessary for the limits of open
excavation to install substructure foundations for both bridge and tunnel Options 2, and 3.
Relatively little temporary easement may be necessary to construct bridge pier footings to frost
depth adjacent to current HCRRA ROW. Substantially more temporary easement may be
required for the installation of the tunnel due to the deeper elevation required for the
installation of the precast box culvert sections, retaining wall footings and any potential soil
corrections necessary below. Both Options 2 and 3 would require use of HCRRA land currently
under lease for private use at the northeast corner of the project, and is not considered an
acquisition as the HCRRA may allow the lease to expire and not be renewed. No temporary
easements in private land are anticipated for the construction of bridge Preferred Option 1.
All bridge and tunnel options can be established within the existing CSAH 19 ( Manitou Road)
and HCRRA right of way. No permanent easements or acquisitions of private land are
anticipated. Refer to Appendix F for property identification information.
Project Costs
A preliminary estimate of project costs was developed based on the three grade separated trail
crossing options presented in this study. A more detailed cost estimate should be performed as
the design elements within the project become more defined.
The estimated project cost for each option C is as follows:
Crossing Option
Cost in 2012 Dollars
Preferred Option 1 (Bridge)
$2.8 million to $3.1 million
Option 2 (Bridge)
$2.8 million to $3.1 million
Option 3 (Tunnel)
$3.3 million to $4.0 million
Page 12 of 16
These costs include a 10% contingency and an estimated 20% for engineering and construction
administration cost. A breakdown of the various components considered when developing
these cost estimates can be found in Appendix G.
The estimated costs apply to any of the structure types suggested previously, as there is
generally less variability in structure type cost for pedestrian bridges than typically expected for
vehicular bridges. This is due to the higher substructure to superstructure ratio that is common
in pedestrian bridges.
The costs shown assume a moderate level of aesthetic treatment on the structure and some
minor site landscaping. The cost difference between the options shown is primarily due to the
area of structure that would be needed to fit the site. The area of structure includes both the
bridge or tunnel structure and retaining walls necessary to keep the grading within the project
site.
An estimated cost of utility relocations can be found in the table in Appendix G, and has been
included in the estimated project costs and in the table above. They have been listed for
budgeting purposes. It is anticipated that utility relocation might be at the cost of the utility
owner. All affected utilities are located in the CSAH 19 or LRT corridor ROW and are assumed
to be under an easement. Both CSAH 19 and the LRT corridor are owned by Hennepin County
agencies. The County may require utility relocations on behalf of the project.
Property Easement and Acquisition Costs
An estimate of property easement costs was developed based on the grade separated trail
crossing options presented in this study. Temporary or permanent easements will be required
for access to provide a temporary trail detour or permanent local trail access points. Temporary
easements will be required for construction of substructures for Options 2 and 3. Permanent
land acquisition is not anticipated for this project.
No cost has been included for temporary or permanent easements within existing public right
of ways as these are typically no cost agreements between agencies. The costs indicated below
are estimates for temporary easements on private lands. Actual costs may be negotiated with
the land owner.
The estimated temporary easement costs:
Crossing Option
Private ROW (SQ FT)
Estimated Unit Value
Total in 2012 Dollars
Preferred Option 1
(Bridge)
0
$0
$0
Option 2 (Bridge)
3,790
$3.60
$13,644
Option 3 (Tunnel)
10,540
$4.45
$46,903
These costs are based on a review of County assessments of market values for affected
properties, and are included in the cost matrix found in Appendix G.
Page 13 of 16
Summary and Recommendations
We believe that a tunnel should not be considered at this location for reasons identified
previously in this report, and that a trail bridge is the most appropriate for the trail crossing. In
addition, we recommend that the location of the bridge be centered in the HCRRA ROW as
indicated in Preferred Option 1, with no consideration for future LRT expansion. Not enough
planning for the LRT system has been completed to date. Adequate conceptual design
information has not been developed or provided at this time regarding the LRT configuration
and requirements at this site to ensure a proposed trail bridge could be constructed to
accommodate the future system.
It is our recommendation that a prefabricated steel truss be used as the main span of the
bridge crossing. The use of a steel truss eliminates the need for a center pier in the existing
median, while also providing a long enough main span to allow for future expansion
considerations for CSAH 19 (Manitou Road) to a 4 -lane undivided urban roadway while still
providing 30 foot horizontal clear zones. This simplifies all pier design and construction such
that the MnDOT crash protection policy may be met without substantial pier protection
measures
There currently are no future plans to widen the roadway at this location, and future expansion
is unlikely. However, placing end piers for the main span farther back from the roadway
provides for wide open sight lines rather than visual obstructions near the sides of the roadway.
A prefabricated steel truss also has the ability to be relocated for future alignment changes. If
the future LRT corridor is designed to consider a shared corridor with the LMLRT Regional Trail,
the main span deck could be removed, and the truss lifted and set on a new alignment. New
substructures could be built while the existing bridge remained in service. This could allow for a
shorter trail closures during future construction.
This structure type tends to be more flexible for aesthetic considerations as well. A wide range
of shapes and paint colors may be considered, as well as the use of self - painting steel. The
structure may be easily adapted to include signage or logos into the truss over the roadway, or
within its railings. Lighting can be included for functional uses such as lighting the trail path, or
for aesthetic presentation of the structure itself. Not all of these aesthetic treatments are
included for consideration in this study, but may be future considerations of the owner or local
stakeholders.
It is also our recommendation that approach ramps be constructed of retaining walls for a
length that provides for 5 to 6 feet of clearance to the low structure member for safety and
maintenance considerations. Approach spans should be constructed with prestressed concrete
beams for their low maintenance advantage over steel girders, and the low visibility of the
approach spans from CSAH 19 (Manitou Road). Refer to Appendix H for a graphical summary of
recommended alignment, profile, structure type, and aesthetic considerations outlined above.
Page 14 of 16
Project Schedule
The Lake Minnetonka LRT Regional Trail & CSAH 19 Safe Crossing project is listed in the
Minnesota Statewide Transportation Policy Plan (STIP) — Project No. 091 - 090 -072, Fiscal Year
2014. The use of Federal Funds is anticipated and the project is listed under Program Category —
EN (Enhancement); and under the Proposed Fund Category — TEA (Transportation
Enhancement).
This is a reimbursable funding program in which the work must first be completed prior to the
availability of Federal funding, and not a grant program. Specific planning milestones must be
met within the program year. The project must be authorized by June 1 st of the fiscal year it
appears in the STIP. Typically, all projects have letting dates set within 90 days of receiving
project authorization.
Refer to Appendix I for an outline of specific planning milestones to be met to achieve Project
Authorization before June 1, 2014, and a recommended project schedule.
Page 15 of 16
Appendix
APPENDIX A Site Photos
APPENDIX B Approach & Crossing Profiles
APPENDIX C Trail Crossing at CSAH 19 (Manitou Road) Alignments
APPENDIX D Structure Type Cross Sections & Examples
APPENDIX E Trail Bridge Concepts
APPENDIX F Existing Site Topography, Utility Considerations & Property
Identification
APPENDIX G Trail Crossing Cost Estimate Matrix
APPENDIX H Trail Crossing Recommendations
APPENDIX I Planning Milestones & Project Schedule
Page 16 of 16
Appendix A
Site Photos
SITE PHOTOS -VIEW LOCATION MAP &01 Ag PEN A
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY Figure 1 of 11
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN Cgn�iultin group, �M1 .
C CL
T
7
N
C
(6
m
N
U
�N N
N p
Ll 14 1
( 4)n uIting Group, Inc.
SITE PHOTOS NEAR 3rd STREET NW
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX A
Figure 2 of 11
VIEW 1
View of Trail Looking West from Trail Intersection with Bay Street (East End of Project)
VIEW 2
View of Trail Looking West from Trail Intersection with Bay Street (East End of Project)
C CL
T
7
N
C
(6
m
N
U
�N N
N p
-_ 1 611 4 -
Corisul#ing Group, Inc.
SITE PHOTOS NEAR 3rd STREET NW
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX A
Figure 3 of 11
VIEW 3
View of East Approach Looking West Along Trail Toward Manitou Road
VIEW 4
View of East Approach Looking East Along Trail from Manitou Road
C CL
T
7
N
C
(6
m
N
U
�N N
N p
-_ 1 611 4 -
Corisul#ing Group, Inc.
SITE PHOTOS NEAR 3rd STREET NW
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX A
Figure 4 of II
VIEW 5
View of Intersection of Trail and Manitou Road from South Looking Northeast
VIEW 6
View of Intersection of Trail and Manitou Road from South Looking North
C CL
T
7
N
C
(6
m
N
U
�N N
N p
1 61 O k i - I
{ 4�rl =u IIingGroup Irhu-
SITE PHOTOS NEAR 3rd STREET NW
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX A
Figure 5 of 11
VIEW 7
View of Intersection of Trail and Manitou Road from North Looking Southwest
VIEW 8
View of Intersection of Trail and Manitou Road from North Looking South
C CL
T
7
N
C
(6
m
N
U
�N N
N p
1 61 14 - 9
Cnnsul#ing Group, Inr.
SITE PHOTOS NEAR 3rd STREET NW
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX A
Figure 6 of 11
VIEW 9
View of West Approach Looking West Along Trail from Manitou Road
VIEW 10
View of West Approach Looking East Along Trail Toward Manitou Road
C CL
T
7
N
C
(6
m
N
U
�N N
N p
Ll 14 1
{ 4)n,,uIting Group, Inc.
SITE PHOTOS NEAR 3rd STREET NW
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX A
Figure 7 of 11
VIEW 11
View of Trail Looking East Along Trail Adjacent to Park (West End of Project)
VIEW 12
View of Trail Looking East Along Trail Adjacent to Park (West End of Project)
VIEW 13
View of Detour - Bay Street Connection from Brentwood Avenue to Trail
C
CL
CU
W
T
7
N
C
(6
m
N
U
�N N
N p
Ll 1 1
Corb%uifing Group, Inc.
SITE PHOTOS NEAR 3rd STREET NW
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX A
Figure 8 of 11
VIEW 14
View of Detour - Bay Street Connection from Trail to Brentwood Avenue
C CL
T
7
N
C
(6
m
N
U
�N N
N p
Ll 14 1
d 4�n,muIting Group, Inc.
SITE PHOTOS NEAR 3rd STREET NW
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX A
Figure 9 of 11
VIEW 15
View of Detour - Looking West Along Brentwood Avenue Towards Manitou Road
VIEW 16
View of Detour - Looking North Along Manitou Road Towards Manitou Park
C CL
T
7
N
C
(6
m
N
U
�N N
N p
Ll 14 1
Cgrcpul#ing Group, Inc.
SITE PHOTOS NEAR 3rd STREET NW
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX A
Figure 10 of 11
VIEW 17
View of Detour - Looking East from Manitou Park Toward Manitou Road
VIEW 18
View of Detour - Looking Southwest from Manitou Park Toward Trail
C
(0
CL
N
C)
ti
T
7
N
C
(6
d
07
[O
n
N
U
�N N
No p
SITE PHOTOS NEAR 3rd STREET NW
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX A
Figure 11 of 11
Appendix 6
Approach & Crossing Profiles
APPROACH TO BRIDGE
AT GRADE RETAINING WALLS
TRAIL
CONNECTION
(TYP.)
TOP OF ELEVATED—
TRAIL
05
APPROX, EXIST
G ROUND LINE
BRIDGE
MAIN SPAN
VERT. CLR
17' -4" MIN.
ASSUMED 3' -0"
STRLICT. DEPTH
—(L CSAH 19
(MANITOU ROAD)
1
APPROX. EXISTING
GROUNDLINE
TYPICAL BRIDGE ELEVATION
(EAST & WEST APPROACH SIMILAR)
�I
i .
n
'n
a
BRIDGE
APPROX.LENGTH
APPROX.LENGTH
TOTAL APPROX.LENGTH
DESCRIPTION
CONCEPT
OF BRIDGE
OF APPROACHES
LENGTH OF STRUCTURE
PREFERRED
635'- 0''
905'- All
1040'- All
ALIGNMENT CENTERED
OPTION I
IN HCRRA R.O.W.
OPTION. 2
635'- All
905'- All
1090'- All
ALIGNMENT AT NORTH
SIDE OF HCRRA R.O.W.
APPROACH TO BRIDGE
END SPANS RETAINING WALLS
.05
—TOP OF ELEVATED
TRAIL
�.T75 f
NOTES
( PIERS TO BE PLACED FOR POTENTIAL FUTURE
WIDENING TO 4 LANES AND 30 FOOT CLEAR
ZONES TO ACCOMMODATE M,DOT PIER
PROTECTION POLICY.
TYPICAL APPROACH & BRIDGE PROFILE
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD. MN
END SPANS
TOP OF ELEVATED
TRAIL
TOP OF ELEVATED .05
TRAIL
0 5
& IS I
Ugn�iul#in& group,
APPENDIX B
Figure 1 of 2
AT GRADE
TRAIL
±360'- 0'' (WEST APPROACH)
TOP OF RETAINI
TRAIL SURFACE WA
i
i
ORNAMENTAL
METAL RAILING
(T YP.)
APPROX. EXIST.
GROUNDLINE
TOP OF
TUNNEL
TRAIL SURFACE
.05 TRAIL SURFACE
144' - 0'' OPTION 3 (14' x 11' PRECAST BOX)
APPROX. PROPOSED 5'_O" MIN.
CSAH IS �j �GROUNDLINF COVER
(MANITOU ROAD)
HEADWALLS
.O1
TYPICAL TUNNEL ELEVATION
�m
n
'n
a
ISDO'- 0'' (EAST APPROACH)
i
i
TRAIL SURFACE - - - - - - - - - - - - - - - - - - - - - - - ;
° OS ��
- - - - - - - - - - - - - - - - - - - - - - - -
AT GRADE
TRAIL
TYPICAL APPROACH & TUNNEL PROFILE
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD. MN
96 �1
Cgn�iuil#in& Croup, Irvt.
APPENDIX B
Figure 2 of 2
- TOP OF RETAINING
WALL
APPROX. EXIST. TRAIL SURFACE
Appendix C
Trail Crossing at CSAH 19 (Manitou Road)
Alignments
1 ,
1
LEGEND & NOTES- r',E
0 BRIDGE STRUCTURE - -
� APPROACH FILL WITH RETAINING WALLS
0 PROPOSED TRAIL ON GRABS
■ ■ ■ EXISTING IO FOOT TRAIL •.� �.� O L
■ ■ ■ TEMPORARY TRAIL DETOUR 50 0 50
PROPOSED TEMPORARY OR SCALE FEET ;•
PERMANENT 10 FOOT TRAIL -
PROPOSED TEMPORARY OR
PERMANENT DRAINAGE CROSSING - - - GIDEON BAY
EXISTING R.O.W. / PROPERTY LINES
TEMPORARY EASEMENT
S•L MAXIMUM SLOPE AT BRIDGE AND APPROACHES =v y� - 1 ?
do
Y
r E
MANITOU
tiA
g7-FL
a
Y \
p l
.` DANBERRY ht'
BL DG. CORD
1 -
oi BRENTWOOD AVENUE
ALL - AMERICAN � J ��- — ��
RECREATION
-
_ P �� LAN -DE- CON -INC. i
-� LANDSCAPING - - - -- - -- ❑
A
Al _ > -
-
IL .
.r s ' . • - 'X, XCEL ENERGY •' ,
ae
m
a> - t
<., L
o 'o �'\ 1 + .
'► dL
z lr '�' �i"• \\\\ A
PREFERRED OPTION 1 - TRAIL BRIDGE CROSSING CSAH 19 (MANITOU ROAD) APPENDIX C
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY Figure 1 of 4
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN c�nud #��� group, �rr-
OPTION 2 - TRAIL BRIDGE CROSSING CSAH 19 (MANITOU ROAD) APPENDIX C
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY & 0 1 Figure 2 of 4
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN Cgn�iultin group, �M1 .
LEGEND & NOTES-
r',E
I
0 TUNNEL STRUCTURE
APPROACH WITH RETAINING WALLS,
�-
0 PROPOSED TRAIL ON GRADE
EXISTING 10 FOOT TRAIL
TEMPORARY TRAIL DE70UR 50
0 50
PROPOSED TEMPORARY OR SCALE
FEET
PERMANENT 10 FOOT TRAIL
-
;•
PROPOSED TEMPORARY OR
PERMANENT DRAINAGE CROSSING
- - -
�
�
-
EXISTING R.O.W. / PROPERTY LINES
-
TEMPORARY EASEMENT�I
S% MAXIMUM SLOPE AT BRIDGE AND APPROACHES
-
do
Y
A ri
GIDEON BAY
E
MANITOU PARK a >> � ♦►
- - ,
iw
it
it T
. - r
F �
DANBERRY ht'
+- DG. CORP.
g
o BL r .
« . b AIM ,
,
.,P
J BRENTWOOD AVENUE
ALL- AMERICAN _ -
-
RECREATION
o - . s# - - off
q - l
1� AN DE CON INC.
P LANDSCAPING - - - - a
r: �k: -
_- ... -
-' _.
s-
- " 'X, - XCEL ENERGY ' A,
•Y IL
M 1. Q 6 y - i INS
,
No •o ."j,. \�5\ 1 + . ,may - 1 -'� - Mr•. " I. "�'.�, a
di..
OPTION 3 - TRAIL TUNNEL CROSSING CSAH 19 (MANITOU ROAD) APPENDIX C
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY Figure 3 of 4
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN "nt"� #��� group, �rr-
X
E
00
T
N
fb
a
12
m
CD
N
U
�N N
N 0
o N i
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING AT CSAH 19 (MANITOU ROAD) FEASIBILITY STUDY
Trail Crossing Approach Option Comparison
APPROX. AREA
APPROX.AREA
APPROX. AREA
APPROX. AREA
APPROX. TEMP.
APPROX. TEMP.
APPROACH
MINIMUM TRAIL
OF BRIDGE OR
OFAPP
OF APP
OF PAVING ON
OFTEMPORARY
UTILITY
EASEMENT ON
EASEMENT ON
OPTION
RADIUS (FT)
TUNNEL
(SQ FT)
GRADE
TRAIL
IMPACTS?
PUBLIC LAND (SQ
PRIVATE LAND
(SQ FT)
(SQ FT)
(SQ FT)
FT)
(SQ FT)
rn
=
Preferred
Option 1
N/A
9130
2900
1070
5270
NO
6750
0
Q
U�
0<
0
�o
Option 2
90
9130
2900
1335
5120
NO
6750
855
wz
=a
U
a�
0
a
Option 3
(Tunnel)
N/A
2256
3620
1720
5270
YES
6750
2960
a
°�'
Q
Preferred
Option 1
3975
9130
2900
420
1540
YES
1375
0
U"
�a
00
,Qp
Lu—
Option 2
90
9130
2900
1735
1540
YES
4720
SEE NOTE 1
2935
wz
=Q
U
O�
a
Option 3
(Tunnel)
3975
2256
3910
200
1540
YES
4055
SEE NOTE 2
7580
Q
NOTE 1: INCLUDES APPROXIMATELY 3,350 SQUARE FEET OF NECESSARY LAND CURRENTLY UNDER LEASE FROM HCRRA.
NOTE 2: INCLUDES APPROXIMATELY 2,685 SQUARE FEET OF NECESSARY LAND CURRENTLY UNDER LEASE FROM HCRRA.
TRAIL BRIDGE CROSSING CSAH 19 (MANITOU ROAD) OPTION MATRIX
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
9 1 APPENDIX C
Figure 4 of 4
Carh$udtirig CrnaF IM1 '.
Appendix D
Structure Type Cross Sections & Examples
15' -5/ ±
i o _
STEEL
TRUSS
MIN.
�A L
LING
12' -0''
CLEAR
ffLDED
GIRDERS
c
7 I
m
m
r`
r`
T
7
Cn
N
C
(6
d
07
[O
N
U
�N N
N p
o�
PREFABRICATED STEEL TRUSS BRIDGE
(BRIDGE MAIN SPAN)
17' -8"
12' -0''
CLEAR
-- BRIDGE
°
WOOD
METAL
RUB PAIL
�a
m
— MN63"
PRESTRESSED
+
CONC. BEAMS
cv
7' -5" 7' -5"
PRESTRESSED CONCRETE THROUGH
GIRDER BRIDGE
(BRIDGE MAIN SPAN)
14
12' -0''
,I FAR
8' -0"
METAL
RAILING
8' -0"
METAL
RAILING
MN63"
PRESTRESSED
CONC. BEAMS
PRESTRESSED CONCRETE GIRDER BRIDGE
(BRIDGE MAIN SPAN)
Ll 14 I
C_paiilul#ing Group, Inc.
14' -6"
STRUCTURE TYPE CROSS SECTIONS APPENDIX D
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY Figure 1 of 6
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
PAVEMENT v
PRECAST CONCRETE BOX
CULVERT TUNNEL
2' -9" I 4' -6'' 4' -6" 12' -9"
t T t l
STEEL GIRDER BRIDGE
(BRIDGE MAIN SPAN)
14' -6"
1
STRUCTURE TYPE:
Prefabricated Steel Truss Bridge
(Main Span Only)
REFERENCE PROJECT:
Pedestrian Bridge Over T.H. 65
Columbia Heights, MN
CONSTRUCTION COST:
$2.0 Million - Constructed in 20010
$2.3 Million - Projected Cost in 2014 Dollars
N
N
ti
T
7
N
C
(6
d
07
[O
N
U
�N N
N p
�m 2
- & I 1 I
_.
Cormul#ing Group, Inr.
STRUCTURE TYPE EXAMPLES
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX D
Figure 2 of 6
C
O1
N
N
T
N
m
N
VN U
No O
STRUCTURE TYPE:
Steel Girder Bridge
REFERENCE PROJECT:
Edinburgh Trail Bridge
Over T.H. 252
Brooklyn Park, MN
CONSTRUCTION COST:
$1.3 Million - Constructed in 2003
$2.1 Million - Projected Cost in 2014 Dollars
Ll 14 I
Con- wilingGroup, Inc.
STRUCTURE TYPE EXAMPLES
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX D
Figure 3 of 6
STRUCTURE TYPE:
Prestressed Concrete Through Girder Bridge
(Main Span Only)
REFERENCE PROJECT:
Trail Bridge Over T.H. 7
Saint Louis Park, MN
CONSTRUCTION COST:
$1.5 Million - Constructed in 2007
$2.0 Million - Projected Cost in 2014 Dollars
N
N
ti
T
7
N
C
(6
d
07
[O
N
U
�N N
N p
�m 2
- & I 1 I
_.
Cormul#ing Group, Inr.
STRUCTURE TYPE EXAMPLES
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX D
Figure 4 of 6
STRUCTURE TYPE:
Prestressed Concrete Girder Bridge
REFERENCE PROJECT:
Trail Bridge Over T.H. 169
Champlin, MN
CONSTRUCTION COST:
N
N
ti
T
7
N
C
(6
d
07
[O
N
U
�N N
N p
�i?tl" v V
x1.4 IMllllon - Gonstructea in 2uu4
$2.1 Million - Projected Cost in 2014 Dollars
- & 1 1 91 4: 1
_.
ConSkilting Group, Inr.
STRUCTURE TYPE EXAMPLES
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX D
Figure 5 of 6
STRUCTURE TYPE:
Precast Concrete Box Culvert Tunnel
REFERENCE PROJECT:
Wayzata Country Club Pedestrian Tunnel
Wayzata, MN
CONSTRUCTION COST:
$0.4 Million - Constructed in 2004
$0.6 Million - Projected Cost in 2014 Dollars
N
d
N
ti
T
7
N
C
(6
d
07
[O
N
U
�N N
N p
�m 2
- & I 1 I
_.
Cormul#ing Group, Inr.
STRUCTURE TYPE EXAMPLES
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX D
Figure 6 of 6
Appendix E
Trail Bridge Concepts
LAKE BRI
K R GIONA TRAIL,CRO B RID GE
FEASIBILITY STUDY &0 Figure 1 of 2
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN Cgn�iultin group, �M1 .
TRAIL BRIDGE CONCEPTS - GIRDER BRIDGE APPENDIX E
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY Fig ure 2 of 2
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN cnud #��� i1rc uP, �M1.
Appendix F
Existing Site Topography, Utility
Considerations & Property Identification
EXISTING SITE TOPOGRAPHY, UTILITY CONSIDERATIONS & PROPERTY IDENTIFICATION APPENDIX F
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY m h I
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN Cgn�iultinj (, rnup, �M1 .
From: tickets(&koroartners.com
To: Casey Black
Subject: NORMAL GeoCall Locate Information - 121012872
Date: Tuesday, April 10, 2012 3:20:07 PM
Gopher State One Call Locate Request
Ticket Number: 121012872 Old Ticket:
By: DI M Source: VOICE
Type: NON- EXCAVATION Date: 4/10/2012 3:19:06 PM
Send To: AutoEmail Sequence: 2
Company Information
SRF CONSULTING GROUP, INC. Type: OTHER
1 CARLSON PARKWAY, SUITE 150
MINNEAPOLIS, MN 55447
Caller: CASEY BLACK Caller Phone: (763) 475 -0010
Contact: CASEY BLACK Contact Phone: (763) 475 -0010
Company Phone: (763) 475 -0010 Company Fax:
Company Email: CBLACK @SRFCONSULTING.COM
Work Information
State:
MN
Work Date:
County:
HENNEPIN
Done For:
Place:
TONKA BAY
Street:
0 COUNTY RD 19
Intersection:
BRENTWOOD AVE
Type of Work:
OTHER -
SEE REMARKS
Explosives:
No
Tunnel /Bore:
Right of Way:
No
Duration:
-----------------------
05/01/2012 3:15:23 PM
THREE RIVERS PARK
No
6 MONTHS
Remarks
----------------------------------------------------
PEDESTRIAN BRIDGE DESIGN
A LISTING OF UTILITIES IS REQUESTED FOR AREA BOUNDED BY SMITHTOWN RD ON THE
SOUTH, WOODLAWN AVE ON THE NORTH, WEDGEWOOD DR ON THE WEST, AND TIMBER LN ON
THE EAST.
CALLER REQUESTS MAPS BE E- MAILED TO CBLACK @SRFCONSULTING.COM OR MAILED TO
CASEY BLACK AT SRF CONSULTING GROUP, INC. 1 CARLSON PARKWAY, SUITE 150,
MINNEAPOLIS, MN 55447
GSOC OP SEES WORK MAY BE IN SHOREWOOD AS WELL
COUNTY RD 19 AKA MANITOU RD
Members
Code Name Phone Number
----------------------------------------------------------------------------
ACCCOMI8 ACCESS COMMUNICATION TECH 7635459998
CSHRWD01 CITY OF SHOREWOOD 9524011637
CTNKBY01 CITY OF TONKA BAY 9524747994
HENDPW01 HENNEPIN COUNTY PUBLIC WORKS 612- 596 -0339
METWAS01 METRO WASTE COMMISSION (651) 602 -4511
MINGAS05 CENTER POINT ENERGY 763 - 559 -5185
MNDCBL01 MEDIACOM 515 - 559 -0032
QLNMNO3 QWEST (800) 283 -4237
XCEL08 XCEL ENERGY 6126304366
Location
---------------------------------------------------------------------- - - - - --
Latitude: 44.9088167008303 Longitude: - 93.6016201929221
Second Latitude: 44.8996965025598 Second Longitude: - 93.5799894618067
T117NR23WS27Qan T117NR23WS28QSE T117NR23WS28QSW
T117NR23WS28Qan T117NR23WS33QNE T117NR23WS33QNW
T117NR23WS33Qan T117NR23WS34QNW T117NR23WS34Qan
From:
tickets(&koroartners.com
To:
Casey Black
Subject:
NORMAL GeoCall Locate Information - 122150491
Date:
Thursday, August 02, 2012 8:33:26 AM
Gopher State One Call Locate Request
---------------------------------------------------------------------- - - - - --
Ticket Number: 122150491 Old Ticket:
By: VISH J Source: VOICE
Type: ENGINEERING DSGN Date: 8/2/2012 8:32:52 AM
Send To: AutoEmail Sequence: 1
Company Information
---------------------------------------------------------------------- - - - - --
SRF CONSULTING GROUP, INC. Type: OTHER
ONE CARLSON PARKWAY NORTH, SUITE 1
PLYMOUTH, MN 55437
Caller: CASEY BLACK Caller Phone: (763) 475 -0010
Contact: CASEY BLACK Contact Phone: (763) 475 -0010
Company Phone: (763) 475 -0010 Company Fax:
Company Email: CBLACK @SRFCONSULTING.COM
Work Information
State:
MN Work Date:
County:
HENNEPIN Done For:
Place:
TONKA BAY
Street:
0 BRENTWOOD AVE
Intersection:
MANITOU RD
Type of Work:
ROAD CONSTRUCTION
Explosives:
No Tunnel /Bore:
Right of Way:
Yes Duration:
-----------------------
08/23/2012 9:00:00 AM
PRELIMINARY BRIDGE
No
1 HOUR
Remarks
---------------------------------------------------------------------- - - - - --
CALLER REQUESTS A MEET FOR 8/23/2012 AT 9:00:00 AM
OTHER WORK TYPE DESCRIPTION: BRIDGE PLANNING
MEET AT THE TRAIL INTERSECTION IMMEDIATELY SOUTH OF THE INTERSECTION OF
BRENTWOOD AVENUE AND CSAH 19 ( MANITOU ROAD) AT THE LOCATION OF THE LAKE
MINNETONKA REGIONAL TRAIL INTERSECTION WITH CSAH 19 ( MANITOU ROAD). FOR THE
WORK TO TAKE PLACE GOING E AND W APPROX 1000E
MARKING INSTRUCTIONS:THIS IS A FIELD MEET TO COORDINATE CONCERNS RELATED TO
THE PLANED CONSTRUCTION OF A TRAIL /PEDESTRIAN BRIDGE AT THE INTERSECTION OF
THE LAKE MINNETONKA REGIONAL TRAIL AND CSAH 19 ( MANITOU ROAD). WE WILL MEET
AT THE CROSSING TO REVIEW FIELD MARKINGS WITH RELATION TO PLANNED BRIDGE
SUBSTRUCTURES.
FIELD MARKINGS WERE PREVIOUSLY COMPLETED UNDER TICKET NUMBER 122052794, AND
SURVEYED. NO NEW MARKINGS ARE REQUIRED FOR THE FIELD MEETING.
ALT CONTACT: JOHN THIESSE - (763) 475 -0010
ORIGINAL FILE: KOR 2012080200198.XML
Members
Code Name
Phone Number
----------------------------------------------------------------------------
CSHRWD01
CITY OF SHOREWOOD
9524011637
CTNKBY01
CITY OF TONKA BAY
9524747994
METWAS01
METRO WASTE COMMISSION
(651) 602 -4511
MINGAS05
CENTER POINT ENERGY
763 - 559 -5185
MNDCBL01
MEDIACOM
515 - 559 -0032
QLNMNO3
QWEST
(800) 283 -4237
XCEL08
XCEL ENERGY
6126304366
Location
Latitude: 44.906548362687 Longitude: - 93.6024378498482
Second Latitude: 44.9029908236669 Second Longitude: - 93.578984444456
T117NR23WS27Qan T117NR23WS28QSE T117NR23WS28QSW
T117NR23WS28Qan T117NR23WS33QNE T117NR23WS33QNW
T117NR23WS33Qan T117NR23WS34QNW T117NR23WS34Qan
L1291 RECORD OF MEETING
Considting Group, Inc.
DATE
CLIENT:
8/23/12 LOCATION: Site
Three Rivers Park District
PURPOSE OF MEETING. Utility Impact Coordination Mtg
ATTENDEES:
Alex Meyer - Three Rivers Park District
Casey Black - SRF
MediaCom, Greg Kluver - City of Tonka Bay, City of Shorewood,
USIC (Locators for Xcel & CenturyLink)
BRIEF SUMMARY OF MEETING:
SRF No. 7768
PROJECT NAME:
Lake Mntka Regional Trail Pre - Planning Study
ROUTE TO:
File
Mike McGarvey
Ca
MediaCom: Indicated they had a cable line and a fiber optic line below Xcel on the power poles running
along the Manitou Road corridor which will be impacted by the bridge. Would need to be buried /relocated
for the preferred bridge option 1. Noted that there was a splice location at approximately the Xcel Energy
parking lot just to the southeast of the project site. Additional contacts: Mike Provos (612- 919 - 0158),
Chris Thompson (612- 730 - 2900), Mike Debner (651- 336- 4252).
City of Tonka Bay: Greg confirmed the water main running along the east side of Manitou Road, and storm
sewer and sanitary sewer alignments. Indicated the water main is old and prone to breaks. The City is interested in replacing,
however no need to do so to accommodate preferred bridge option 1.
City of Shorewood: Confirmed storm sewer drainage alignments. Noted that the City regularly plowed the
trail in the winter, and would require an adequate structure for maintenance vehicles.
USIC: Confirmed Xcel on power poles. Noted buried condition should be possible, but coordinated with Xcel directly.
(Attach Additional Minutes)
ACTION NEEDED: RESPONSIBILITY:
1) Review MediaCom impacts with provided contacts SRF
2) Review Xcel impacts and required efforts SRF
Form No. 1014 Rev. 01/11
Ll Oki
Consulting Group, Inc.
SRF No. 7768
RECORD OF TELEPHONE CONVERSATION
Route to
FILE
Copy to
Date 8/23/2012 Time
Employee CASEY BLACK
Conversation with CHRIS THOMPSON
Telephone 612- 730 -2900
Organization MEDIACOM
Re. Lake Minnetonka LRT Regional Trail - Util
Relocation
DETAIL O F CO NVER S ATI O N
Called Chris to discuss the necessary relocation of both the MediaCom cable line and fiber optic lines
suspended from Xcel's overhead power poles that are impacted by the alignment of both Preferred
Option 1 and Option 2 bridge alignments. He indicated that he could put together a cost estimate for
line relocations based on draft bridge concept layouts. SRF provided the layout for Preferred Option 1
for Chris' reference. It was noted to Chris that the Xcel power lines would also need relocation, not just
the suspended MediaCom lines. Chris indicated that a 12 to 18 month lead time would be necessary to
have the lines relocated prior to project construction. This could be coordinated with MediaCom through
Chris. His e -mail address is CTHOMPSON1 @MEDIACOMCC.COM
1:00 P.M.
Appendix G
Trail Crossing Cost Estimate Matrix
a
00
r-
T
N
a
m
oo
CD
N
U
_ N
2
LAKE MINN ETON KA LRT REGIONAL TRAIL CROSSING AT CSAH 19 (MANITOU ROAD) FEASIBILITY STUDY
Trail Crossing Cost Estimates by Crossing Option (2012 Dollars)
APPROACH
BRIDGE/
TUNNEL
ESTIMATED
ESTIMATED
STRUCTURE
ESTIMATED
APPROACH
CONTINGENCY
ENG. &ADMIN.
UTILITYIMPACT
ESTIMATED PROJECT
ROW
EASEMENT/
ESTIMATED TOTAL
OPTION
STRUCTURE
COST /SF
COST
& TRAIL
(10 %)
(20 %)
COST
COST (2012 DOLLARS)
ACQUISITION
COST (2012 DOLLARS)
AREA (SF)
COST
COST
$200
$1,826,000
$230,000
$2,807,580 LOW EST.
$2,807,580 LOW EST.
PREFERRED
OPTION 1
9130
$233,860
$467,720
$50,000
$0
$220
$2,008,600
$330,000
$3,090,180 HIGH EST.
$3,090,180 HIGH EST.
$200
$1,826,000
$230,000
$2,807,580 LOW EST.
$2,821,224 LOW EST.
OPTION 2
9130
$233,860
$467,720
$50,000
$13,644
$220
$2,008,600
$330,000
$3,090,180 HIGH EST.
$3,103,824 HIGH EST.
$655
$1,477,680
$730,000
$3,272,112 LOW EST.
$3,319,015 LOW EST.
OPTION 3
(TUNNEL)
2256
$288,144
$576,288
$200,000+
$46,903
SEE NOTE 1
$865
$1,951,440
$930,000
$3,945,872 HIGHEST.
$3,992,775 HIGHEST.
1) UTILITY COSTS FOR AN OPEN CUT TUNNEL INSTALLATION WILL LIKELY EXCEED $200,000 AND INCLUDE MULTIPLE IMPACTS TO PUBLIC AND PRIVATE UTILITIES.
NOTES:
THIS COST HAS BEEN INCLUDED IN THE ESTIMATED PROJECT COSTS LISTED ABOVE.
TRAIL CROSSING COST ESTIMATE MATRIX
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
9 1 APPENDIX G
Figure 1 of 1
Carh$udtirig GrnuP, Irhi
Appendix H
Trail Crossing Recommendations
I
I
I
PROPOSED TEMP.
—
TRAIL DETOUR
2'-4"
(T YP.)
I
BEGIN BRIDGE
BEGIN APPROACH STA. 12+81.58
STA_ 10 +82.00 EL. 950.00
EL. 940.D2
0
236' -0" APPROACH SPANS
118' -0" 118' -0"
AE= 91 ° -58'- 07.2"
IF LMLRT
REGIONAL TRAIL (TRAILI)
1
PROPOSED TEMP.
\ — — TRAIL DETOUR
632'-2"
STEEL TRUSS MAIN SPAN
160' -2"
SPAN 3
VERT. CLR. V ° N
PT. 'A'
N
CC�� CSAH 19 J\
(MAN 170U ROAD)
r a
GENERAL PLAN
SCALE 0 50
236' -0" APPROACH SPANS
118' -0" 118.' -0"
SPAN 4 SPAN 5
- - END BRIDGE—
STA. 19 +18.42
EL. 950.00.
END APPROACH
STA. 21 +18.00
EL. 940.02
NOTES-
O CONTROL POINT
LMLRT REGIONAL TRAIL (TRAILD
A. 16 +00.00
IF CSAH 19 (MANIIOU ROAD)
X =446078.423
Y= 141684.698
DESIGN DATA
2012 AND CURRENT INTERIM AASHTO LRFD
BRIDGE DESIGN SPECIFICAT IDNS
2009 AASHTO LRFD GUIDE SPECIFICATIONS FOR
DESIGN
OF PEDESTRIAN BRIDGES
LOAD AND RESISTANCE FACTOR DESIGN METHOD
90 psf or HIS TRUCK LIVE LOADING
MATERIAL DESIGN PROPERTIES:
REINFORCED CONCRETE:
t = 4,000 psI n = B
Fy = 60,000 psl REINFORCEMENT
PRESTRESSED CONCRETEe
P'c = 9,000 psI n = 7
is - 2T,000 psi LOW RELAXATION STRANDS
STRUCTURAL STEELE
Fy = 50,000 psI STRUCIURAL STEEL SPEC.
3309
Fy = 36,000 psi STRUCTURAL STEEL SPEC.
3306
STRUCTURAL TUBING PER 3361 TYPE C
DESIGN SPEED : UNDER - 35 mph
APPROXIMATE DECK AREA 9060 ft 2
LIST OF SHEETS
1 GENERAL PLAN & ELEVATION
2 AESTHETIC DETAILS
0 0
0
T
Qo i-o
77 o PROPOSED TYPE OF STRUCTURE
VPI STA. IGLOO
.m
>? VPI EL. 965.92 » SUPERSTRUCTURE:
w PROPOSED FINISHED M G 220 5 VERT. CLEAR C TOP OF ORNAMENTAL -L -MAIN SPAN:
ADE AT.'A'= 17' -6" RAILING PREFABRICATED STEEL TRUSS
rl r �„
+5 OO PR
PROFILE GR - -5.00% �� - APPROACH SPANS III E ;
ROW--{ --ROW 36" PRESTRESSED CONCRETE BEAMS
-T" (MIN.) CONCRETE DECK
CSAH -NO OVERLAY
(MANI ROAD) -ALL BARS EPDXY COATED
SPAN 1 SPAN 2 SPAN 3 SPAN 4 SPAN 5 SUBSTRUCTURES:
WEST ABUTMENT PIER N0.1 PIER N0.2 PIER N0.3 PIER N0.4 EAST ABUTMENT - PARAPET TYPE ABUTMENTS SUPPORTED
ON PILING OR SPREAD FOOTINGS
GENERAL ELEVATION -PIERS SUPPORTED ON PILING OR SPREAD FOOTINGS
SCALE D 5 0
��,� E N G I N E E R S ONE CARLSON PARKWAY NORTH
14.' -O" DECK WIDTH 72' -0" CLEAR P n N N e Rs P FAM�T 63 4 s zaze TH.MN 55447
PHa 763- 4 11KIA D
D WW,F 763 475- N 29 OM
— 0" Consulting Group, Inc.
12'_0" CLEAR 1' -0" .Ol
.01 /, STEEL TRUSS MINNESOTA
° ° 6 -0 a DEPARTMENT OF TRANSPORTATION
.07 % ° FCF TRAIL
2" (TYP.) PRELIMINARY PLAN
a rTYPe) TRAIL ! BRIDGE NO. XX
PROFILE @ ' +� ° LAKE MINNETONKA LRT REGIONAL TRAIL PEDESTRIAN
GRADE CONC. M 7" MIN. q ETA _6" - - PROFIL GRADE E 4' -6" MIN. BRIDGE OVER CSAH 19 (M ANITOU ROAD)
L +� o _ METAL 2.03 MILES NW OF JCT. T.H. 7 AND CSAH 19
DECK RAILING RAILING
SPAN I.D. NO. - MAIN SPAN 302 & APPROACH RAMPS 501
o GENERAL PLAN & ELEVATION
3.6M" PRESTRESSED SEC. 33, T117N, R23W,
CONCRETE BEAMS
FLOOR BEAM - CITIES OF FORKS BAY AND SHOREWOOD
BRIDGE MOUNTED THREE RIVER PARK DISTRICT
3'-6" 3'-6" 3' -6" 3' -6" REINFORCED SIGN TYPE D (TYP.)
CONCRETE DECK
TRANSVERSE SECTION TRANSVERSE SECTION APPROVED:
TRaFE RIVERS PARK msTR1cT REPRESE NTATIVE DAFE
APPROACH SPANS MAIN SPAN
APPROVED:
STATE BR]DGE ENG]NEER DATE
DES. CB DR. ER,1 I BrldQa No. Comm. No..
CHKt X CHI SHEET 1 OF 2 X 7765
... \BR \Plans \Study \7768- 0Ph_].dgn
160' -0'' (OUT -TO -OUT OF TRUSS)
X
THREE RIVERS PARK DISTRICT _ TOP LOGO TO BE FABRICATED WITH CHORD F & ORNAMENTAL
TRUSS (TYPI.CAL EACH SIDE)
METAL RAILING TYPE
SPECIAL 2
z
TOP OF CONCRETE CURB
z —TOP OF ORNAMENTAL PROFILE GRADE
_
METAL RAILING TYPE
SPECIAL 2 _
Q
BOTTOM OF BOTTOM CL MAIN SPAN AND TRUSS
CHORD
TRUSS ELEVATION
I
TRAIL
I
I
I
2' -10"
�CL TRAIL
18' -0"
I
ORNAMENTAL METAL— o
RAILING TYPE -
SPECIAL 1 °
I
22 2i
I I
o
0
0 RECESS 1
F
—SMOOTH C ONC.
SURFACE FINISH I I
- CONST.
JOINT
o (FIELDSTONE) EXTURE
m
0
a
m
N THREE RIVERS PARK DISTRICT SHEET
E .JO JOHNSO N E N G I N E E R S
BRIDGE NO. DESIGNED KBY P L A N N E R S AESTHETIC DETAILS 2
C. X CHECKED BY D E S I G N E R S LAKE MINNETONKA LRT REGIONAL TRAIL OF
C onsalLing Group
.. \BR \PIOnS \Study \7768_Opn_2.tlgn COMM. Noe 7768 , Inc.
PEDESTRIAN BRIDGE 2
Appendix
Planning Milestones & Project Schedule
c
- o
m
00
T
N
C
fb
a
m
w
CD
ti
N
U
_ N
2
LAKE MINN ETON KA LRT REGIONAL TRAIL CROSSING AT CSAH 19 (MANITOU ROAD) FEASIBILITY STUDY
PROPOSED PROJECT SCHEDULE
PROJECT TASK
DESCRIPTION
TASK ACTIVITIES
2012
2013
2014
2015
SEPT
OCT
NOV
DEC
JAN
FEB
MAR
APR
MAY
JUNE
JUL
AUG
SEPT
OCT
NOV
DEC
JAN
FEB
MAR
APR
MAY
JUNE
JUL
AUG
SEPT
OCT
NOV
DEC
JAN
FEB
MAR
APR
MAY
JUNE
JULY
FEASIBILITY STUDY
PRE - PLANNING REPORT
APPROVED
PROPERTY EASEMENT
/ ACQUISITION
(As Necessary)
Appraisals
Offers
90 Day Waiting Period
Right -of -Way Certificate
DESIGN CONSULTANT
SELECTION
Issue Request for
Proposals
Receive Proposals
Selection
Contract in Place
PROJECT
MEMORANDUM
(MnDOT PM Approval)
SHPO & Permit Process
SEE
NOTE
1
Project Memo to Metro
project Memo to SALT
CONSTRUCTION
PLANS
Coordination Activities
(Soils Report, etc.)
Prepare &Review of
Preliminary Plans
Prepare &Review of Final
Plans
Signed Plans
Project Approved and
Authorized
BID OPENING
CONSTRUCTION
TRAIL CROSSING OPEN TO PUBLIC
NOTES
1) PROJECT MUST BE AUTHORIZED BY THE BEGINNING OF THE MONTH (JUNE 1, 2014)
PLANNING MILESTONES & PROJECT SCHEDULE
LAKE MINNETONKA LRT REGIONAL TRAIL CROSSING FEASIBILITY STUDY
FOR THREE RIVERS PARK DISTRICT IN THE CITIES OF TONKA BAY & SHOREWOOD, MN
APPENDIX I
Figure 1 of 1
con$ultin?, Gropp, Inc-