14-001CITY OF SHOREWOOD
RESOLUTION NO. 14 -001
A RESOLUTION APPROVING WORK ORDER 6 FOR
SMITHTOWN ROAD SIDEWALK IMPROVEMENTS
SAP 216 - 101 -004
CITY PROJECT 13 -04
WHEREAS, the City of Shorewood Council awarded the contract for the construction of
sidewalk along the southerly side of Smithtown Road from the City boundary with Victoria to the
Lake Minnetonka (LRT) Regional Trail (approximately 10,000 feet in length) to Chard Tiling and
Excavating, Inc. of Belle Plaine, Mimnesota; and
WHEREAS, the Capital Improvement Plan provides $1,200,000 for the improvement
project; and
WHEREAS, Work Orders 1 through 5 were necessary to construct the storm drainage
system and associated work previously recommended by staff and approved by the City Council;
and
WHEREAS, Work Orders 1 through 5 increased the project construction costs in the
amount of $37,726.71, from the original contract amount $1,070,672.75 to $1,108,399.46; and
WHEREAS, Work Order 6 will increase the project construction costs in the amount of
$9,396.95, from the current contract amount $1,108,399.46 to $1,117,796.41;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Shorewood,
Minnesota:
Work Order 6 in the total amount of $9,396.95 is hereby approved.
ADOPTED BY THE CITY COUNCIL OF THE CITY OF SHOREWOOD this 13th
day of January, 2014.