14-003CITY OF SHOREWOOD
RESOLUTION NO. 14 -003
A RESOLUTION ACCEPTING IMPROVEMENTS FOR
2013 BITUMINOUS MILL AND OVERLAY PROJECT
AND AUTHORIZING FINAL PAYMENT
CITY PROJECT NO. 13 -05
WHEREAS, on September 9, 2013, the City of Shorewood entered into a
contract with GMH Asphalt Corporation for City Project 13 -05 for the 2013 Bituminous
Mill and Overlay Project; and,
WHEREAS, the Contractor has substantially completed the project work and has
requested City acceptance of the project and final payment for the work performed and
documented to date; and,
WHEREAS, the City Engineer has made final inspection of the project and
recommends acceptance and final payment be made by the City.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of
Shorewood as follows:
The City hereby accepts the work completed pursuant to said contract and
authorizes final payment to the Contractor, and all warranties shall commence as of the
date of this resolution.
ADOPTED BY THE CITY COUNCIL OF THE CITY OF SHOREWOOD
this 13th day of January, 2013.
ATTEST:
Je n Panchyshyn, City C erk
ma
Sc t Zerby, ayo