16-053CITY OF SHOREWOOD
RESOLUTION NO. 16 -053
A RESOLUTION APPROVING CHANGE ORDER NO.2 FOR
STAR LANE AND STAR CIRCLE UTILITY AND STREET IMPROVEMENTS
CITY PROJECT 14 -11
WHEREAS, the City of Shorewood Council awarded the contract for the Star Lane and
Star Circle Utility and Street Improvements Project (City Project 14 -11), on May 26, 2015 to Valley
Paving, Inc. of Shakopee, Minnesota; and
WHEREAS, Change Order No. 1 was necessary to construct the improvements and
associated work previously recommended by staff and approved by the City Council; and
WHEREAS, Change Order No. 1 increased the project construction costs in the amount of
$7,334.84, from the original contract amount of $665,018.13 to $672,352.97; and
WHEREAS, Change Order No. 2 is necessary to construct the improvements and
associated work to accommodate adjacent construction activities to minimize disruption to the
traveling public; and
WHEREAS, Change Order No. 2 will extend the project completion date to August 31,
2016, from the original contract completion date of June 30, 2016. Change Order No. 2 does not
increase the contract amount.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Shorewood,
Minnesota:
1. Change Order No. 2 is approved, extending the contract completion date to August
31, 2016.
ADOPTED BY THE CITY COUNCIL OF THE CITY OF SHOREWOOD this 25th
day of July, 2016.
ATTEST:
Q�t-A- P-66
Je n Panchyshyn, Cqty derk
Sco erby, a r