16-069CITY OF SHOREWOOD
RESOLUTION NO. 16 -069
A RESOLUTION APPROVING WORK ORDER 2 FOR
THE SMITHTOWN ROAD EAST SIDEWALK EXTENSION PROJECT
CITY PROJECT 14 -10
WHEREAS, THE City of Shorewood Council awarded the contract for the construction
of sidewalk along the south side of Smithtown Road located between the Lake Minnetonka
Reginal Trail (LRT) and Country Club Road to S. M. Hentges, Inc. of Jordan, Minnesota; and
WHEREAS, Change Order No. 1 was necessary to construct the improvements and
associated work previously recommended by staff and approved by the City Council; and
WHEREAS, Change Order No. 1 increased the project construction costs in the amount
of $3,366.00, from the original contract amount of $769,873.00 to $773,239.00; and
WHEREAS, Work Order 2 is necessary to provide safety to the traveling public along
Smithtown Road (east bound traffic) and accommodate road drainage to the newly installed
concrete curb and gutter currently impacted due to "rutting" within the travel lane along
Smithtown Road and associated work; and
WHEREAS, Work Order 2 will increase the project construction costs in the amount of
$85,805.00, to $859,044.00;
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of
Shorewood as follows:
Work Order 2 in the total amount of $85,805.00 is hereby approved.
ADOPTED BY THE CITY COUNCIL OF THE CITY OF SHOREWOOD this 22nd
day of August, 2016.
ATTEST:
Jeqn Panchyshyn, CiiFy C1 &k
Scott erby, yo