Change Order No. 1 CHANGE ORDER NO. 1
2016 TRUNK WATERMAIN EXTENSION PROEECT NOVEMBER 9,2016
CITY OF SHOREWOOD,MN
WSB PROJECT NO.2925-16
OWNER: CONTRACTOR:
CITY OF SHOREWOOD WIDMER CONSTRUCTION LLC.
5755 COUNTRY CLOUB ROAD 9455 COUNTY ROAD 15
SHOREWOOD,MN 55331 MAPLE PLAIN,MN 55359
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
After initial pavement removal operations on Yellowstone Trail,the existing bituminous pavement was found to have traces of
geotextile between the lifts of pavement. The traces of geotextile designated the remove bituminous to be contaminated and requiring
additional trucking to dispose of the material properly. Additionally, due to construction, a tree originally identified to be protected
during construction was deemed neccessary to remove to facilities water service installation. The size and location of the tree due to
the proximity of private utilities, required additional costs to clear and grub the tree.
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY,SHAPE, OR FORM
ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE: $1,102,856.13 ORIGINAL CONTRACT TIME: 8/15/2017
PREVIOUS CHANGE ORDERS: $0.00 NET CHANGE FROM PREVIOUS CHANGE ORDERS: NONE
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER: $1,102,856.13 CONTRACT TIME PRIOR TO THIS CHANGE ORDER: 8/15/2017
NET INCREASE OF THIS CHANGE ORDER: $21,293.25 NET INCREASE OF CHANGE ORDER: NONE
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS: $1,124,149.38 CONTRACT TIME WITH APPROVED CHANGE ORDERS 8/15/2017
RECOMMENDED BY: APPROVED BY:
PAUL HORNBY, PE,PROJECT M CONTRACTOR SIGNATURE
WSB&ASSOCIATES,INC. WIDMER CONSTRUCTION LLC.
ENGINEER X f CONTRACTOR
APPROVED BY:
CITY ENGINEER CITY ADMINISTRATOR
�:ii m1 ZP?)-17
DATE DATE
K:102925-16014dminlConstruction AdminlChange Orders)
Page 1 of 1 2925-16 1 1 1 111416GO 1
CHANGE ORDER NO. 1 DETAIL
2016 TRUNK WATERMAIN EXTENSION PROEJCT NOVEMBER 9,2016
CITY OF SHOREWOOD,MN
WSB PROJECT NO.1459-97
ADDED ITEMS
Item No. Mat. No. Description Qty Unit Price Extended Amount
101 2101.511 CLEAR&GRUB 1 L S $2,640.00 $2,640.00
102 2105.607 HAUL AND DISPOSE OF CONTAMINATED MATERIAL 1 LS $18,653.25 $18,653.25
TOTAL ADDED ITEMS CHANGE ORDER NO. 1 $21,293.25
DELETED ITEMS
Item No. Mat.No. Description Qty Unit Price Extended Amount
TOTAL DELETED ITEMS CHANGE ORDER NO. 1 $0.00