Change Order No.2CHANGE ORDER NO. 2
2016 TRUNK WATERMAIN EXTENSION PROEJCT JANUARY 4, 2017
CITY OF SHOREWOOD, MN
WSB PROJECT NO. 2925 -16
OWNER:
CITY OF SHOREWOOD
5755 COUNTRY CLUB ROAD
SHOREWOOD, MN 55331
CONTRACTOR:
WIDMER CONSTRUCTION LLC.
9455 COUNTY ROAD 15
MAPLE PLAIN, MN 55359
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
DURING THE COURSE OF CONSTRUCTION, THE FOLLOWING ITEMS WERE IDENTIFIED THAT WERE NOT ANTICIPATED PRIOR
TO THE START OF CONSTRUCTION:
1. GIVEN THE INCLEMENT WEATHER DURING THE TIME OF CONSTRUCTION, THE EXPOSED SUBGRADE WAS FOUND TO BE
IN SUCH CONDITION THAT SUPPLEMENTAL, STABILIZING AGGREGATE WAS NECCESSARY TO PROVIDE ACCESS TO
RESIDENTS.
2. IN ORDER TO PRESERVE THE NEWLY INSTALLED CONCRETE CURB AND GUTTER, A TEMPORARY BITUMINOUS WEDGE
WAS INSTALLED UNTILL FINAL PAVING CAN BE COMPLETED IN THE SPRING OF 2017.
3. FOLLOWING INSTALLATION OF THE STORM SEWER FACILITIES, ADDITIONAL GRADING OF THE DITCHES WAS
NECCF_SSARY TO CONVEY DRAINAGE. EROSION CONTROL BLANKET WAS INSTALLED TO ENSURE THE NEWLY GRADED
DITCHES WOULD NOT ERODE IN THE SPRING OF 2017.
ADDITIONALLY, IT WAS IDENTIFIED A BID ITEM WAS NOT INCLUDED FOR THE INSTALLATION OF THE STREET ID SIGNS
THROUGHOUT THE PROJECT. AS THESE SIGNS WILL BE REPLACED WITH THE PROJECT, THE CONTRACTOR HAS PROVIDED
A COST ASSOCIATED WITH THE WORK.
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR FORM
ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE:
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS:
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER:
NET INCREASE OF THIS CHANGE ORDER:
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS
RECOMMENDED BY:
PAULHORNBY,PE,PROJECT
WSB & ASSOCIATES, INC.
ENGINEER
APPROVED BY:
CITY ENGINEER
pyaL
CHANGE IN CONTRACT TIME:
$1,102,856.13
ORIGINAL CONTRACT TIME:
8/15/2017
$21,293.25
NET CHANGE FROM PREVIOUS CHANGE ORDERS:
NONE
$1,124,149.38
CONTRACT TIME PRIOR TO THIS CHANGE ORDER:
8/15/2017
$7,794.11
NET INCREASE OF CHANGE ORDER:
NONE
$1,131,943.49
CONTRACT TIME WITH APPROVED CHANGE ORDERS:
8/15/2017
APPROVED BY:
< CONTRACTOR SIGNATURE
WIDMER CONSTRUCTION LLC.
CONTRACTOR
r CITY ADMINISTRATOR
DATE
K:1029254601Ad.WG.nsbuction AdminiChange 0,d—ICI—g. Order No. 21
Page 1 of 1 292546 CO2 122916CO 2
CHANGE ORDER NO. 2 DETAIL
2016 TRUNK WATERMAIN EXTENSION PROEJCT JANUARY 4, 2017
CITY OF SHOREWOOD, MN
WSB PROJECT NO. 2925-16
Item No.
Mat. No.
Description
Qty
Unit
Price
Extended Amount
105
2105.543
STABILIZING AGGREGATE
153.03
TON
$29.70
$4,544.99
106
2360.501
TEMORARY BITUMINOUS WEDGE
8
TON
$322.61
$2,580.88
107
2564.602
SIGN PANELS TYPE SPECIAL
7.5
S F
$48.25
$361.88
108
2575,523
EROSION CONTROL BLANKET CATEGORY 3
222
S Y
$1.38
$306.36
- t
TOTAL ADDED ITEMS CHANGE ORDER NO. 2 $7,794.11