17-035CITY OF SHOREWOOD
RESOLUTION NO. 17 -035
A RESOLUTION APPROVING CHANGE ORDER 3 FOR THE
2016 TRUNK WATERMAIN EXTENSION PROJECT
CITY PROJECT 16 -04
WHEREAS, THE City of Shorewood Council awarded the contract for the 2016
Trunk Watermain Extension Project (City Project 16 -04) on September 26, 2016 to
Widmer Construction LLC. of Maple Plain, Minnesota; and
WHEREAS, Change Order No. 1 and Change Order No. 2 were necessary to
construct the improvements and associated work previously recommended by staff and
approved by the City Council; and
WHEREAS, Change Order No. 1 and Change Order No. 2 increased the project
construction costs in the amount of $29,087.36, from the original contract amount of
$1,102,856.13 to $1,131,943.49; and
WHEREAS, Change Order 3 is necessary to address poor subgrade material
along roadways north of T H7; and
WHEREAS, Change order 3 will increase the project construction costs in the
amount of $22,931.11, to $1,154,874.60;
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of
Shorewood as follows:
1. Change Order 3 in the total amount of $22,931.11 is hereby approved.
ADOPTED BY THE CITY COUNCIL OF THE CITY OF SHOREWOOD
this 24`h day of April, 2017.
..
Sc�Ierby, ayor
ATTEST: