Change Order No. 3 CHANGE ORDER NO.3 2016 TRUNK WATERMAIN EXTENSION PROEJCT APRIL 19,2017 CITY OF SHOREWOOD,MN WSB PROJECT NO.2925-16 OWNER: CONTRACTOR: CITY OF SHOREWOOD WIDMER CONSTRUCTION LLC. 5755 COUNTRY CLOUB ROAD 9455 COUNTY ROAD 15 SHOREWOOD,MN 55331 MAPLE PLAIN,MN 55359 YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION: DURING THE COURSE OF CONSTRUCTION,THE FOLLOWING ITEMS WERE NECCESSARY TO CONSTRUCT THE ROADWAY SUBGRADE: 1. GIVEN THE INCLEMENT WEATHER DURING THE TIME OF CONSTRUCTION AND THE CONDITION OF THE EXISTING SUBGRADE,THE EXPOSED SUBGRADE WAS FOUND TO BE IN SUCH CONDITION THAT ADDITIONAL EXCAVATION, PREPARATION OF THE SUBGRADE,AND INSTALLATION OF SUPPLEMTNTAL MATERIAL WAS NECCESSARY TO STABILIZE THE ROADWAY. COSTS ASSOCIATED WITH THE"MUCK EXCAVATION"INCLUDE LABOR,TIME AND MATERIALS TO COMPLETE THE WORK AS INVOICED HAVE BEEN INCLUDED WITH THIS CHANGE ORDER. 2. VARIOUS LOCATIONS THROUGHOUT THE PROJECT REQUIRED ADDITIONAL SUBGRADE EXCAVATION AND GEOTEXTILE FABRIC TO REMEDIATE POOR MATERIALS ENCOUNTERED DURING EXCAVATION. BID ITEMS FOR SUBGRADE EXCAVATION AND GEOTEXTILE FABRIC AND THE QUANTITIES COMPLETED TO DATE HAVE BEEN INCLUDED WITH THIS CHANGE ORDER. 3, UPON FINAL APPROVAL OF THE MNDOT PERMIT TO INSTALL THE WATERMAIN UNDER TH 7,ADDITIONAL TRAFFIC CONTROL WAS NECCESSARY TO COMPLY WITH THE PERMIT REQUIREMENTS. COST ASSOCIATED WITH FURNISHING AND RELOCATING THE ADDITIONAL TRAFFIC BARRIERS HAVE BEEN INCLUDED WITH THIS CHANGE ORDER. IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY,SHAPE,OR FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE. CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME: ORIGINAL CONTRACT PRICE: $1,102,856.13 ORIGINAL CONTRACT TIME: 8/15/2017 PREVIOUS CHANGE ORDERS: $29,087.36 NET CHANGE FROM PREVIOUS CHANGE ORDERS: NONE CONTRACT PRICE PRIOR TO THIS CHANGE ORDER: $1,131,943.49 CONTRACT TIME PRIOR TO THIS CHANGE ORDER: 8/15/2017 NET INCREASE OF THIS CHANGE ORDER: $22,931.11 NET INCREASE OF CHANGE ORDER: NONE CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS: $1,154,874.60 CONTRACT TIME WITH APPROVED CHANGE ORDERS: 8/15/2017 RECOMMENDED BY: APPROVED BY: PAUL HORNBY,PE,PROJECT-M CONTRACTOR SIGNATURE i WSB&ASSOCIATES,INC. WIDMER CONSTRUCTION LLC. ENGINEER CONTRACTOR APPROVED BY: CITY ENGINEER CIT�Y `DMINISTRATOR DATE DATE K:102 925-16 01AdminWonsfruction Adminichange OrderslChange Order No,31 Page 1 of 1 2925-16 CO3 041917CO 3 CHANGE ORDER NO. 3 DETAIL 2016 TRUNK WATERMAIN EXTENSION PROEECT APRIL 19,2917 CITY OF SHOREWOOD,MN WSB PROJECT NO.2925-16 ADDED ITEMS Extended Item No. Mat.No. Description Qty Unit Price Amount 109 2105.505 MUCK EXCAVATION 115 C Y $86.05 $9,895.46 110 2105.507 SUBGRADE EXCAVATION 136 C Y $31.13 $4,234.02 111 2105.604 GEOTEXTILE FABRIC TYPE V 1273 S Y $2.63 $3,341.63 112 2563.601 TRAFFIC CONTROL 1 L S $5,460,00 $5,460.00 TOTAL ADDED ITEMS CHANGE ORDER NO. 3 $22,931.11 DELETED ITEMS Extended Item No. Mat.No. Description Qty Unit Price Amount TOTAL DELETED ITEMS CHANGE ORDER NO. 3 $0.00 K:10 2 92 5-1 6%4dminlConstruction AdminlChange OrdersXhange Order No.A Page 1 of 1 2925.16 CO3 041917CO 3 Detail I ice CORPORATION GMH ASPHALT Extra Work Invo' 9Ya0 LgKEfOWN ROAD-CHASKA MN 55318 Date: 11!812016 PHONE 952.442.5288 FAX 952.142.5656 To.Widmer Construction LLC 9455 County Road 15 Maple Plain, MN 55359 °a=� — --- --Explanation of Work Invoice Date:+111812016 -- ___-- _ _ �M WORK ON SOFT SPOTS AT PAF2K STREET Jo5�624-Shorewrood-Widmer ! , crition -- _ —� t�— -- _ BACKHOE OPERATOR — ------ i° — 1 nit Price .._cunt 1� 8.75 HR 235.00 2,056.25 SKID LOADER�OPERATOR TRUCKING 6.00 HR 160.00 960.00 17.25 HR 95,00 1,638.75 LABOR 11.00 HR FABRIC 85.00 935.00 CL5 LIMESTONE 478.00 SY 2.50 1,195.00 DUMPSITE FEE 209.98 TN 9.45 1,984.31 15% MARKUP ON MATERIALS 143.00 CY 2.50 357.50 1.00 LS 297.64 297.64 Current Invoice $ 9,424.45 Additional Notes; BRYAN ROCK PRODUCTS, c. Box 215®Shakopee, MN 55379 Phone(952)445 -3900'(800)382-3756-Fax(952)445-0809 www.br-yanrock.com INVOICE 18736 ACCOUNT NO 0135 PAGE 3 SOLD To G M H ASPHALT DATE 10/3102016 9180 LAKETOWN ROAD CHASKA,MN 55318 TERMS Net 30 Days SHOREWOOD*1624 Ticket Date PO Order Location Product ­-Materjals-- --.-Freight---- Fee Tax Qty Rate Amount Rate Amount Amount Amount Total 133828 10/241201( 60749 103 1"With Fire, 10.42 8.80 102.10 0,00 0,00 0.00 11.79 173.89 133831 IW4/201( 60749 103 11"With FinL-,. 18.39 133835 10/241201( 60749 103 11"With Finei 17,68 8.80 161.83 0.00 0.00 0,00 11.77 173.60 133840 10/241201( 60749 103 1"With Fine.- 18.16 5.80 154.70 0,00 0.00 0.00 11.25 165.95 133841 10/24/201( 8.80 159-81 on 0.00 0.00 11-83 171.44 60749 103 1"With Finat 18.10 8.80 159,28 0.00 0.00 0.00 11.59 170.87 133844 IM41201f 60749 103 1"W1th Mw 10.45 8.80 162.36 o.co 0.00 0.00 11.81 174-17 133846 10/24/201f 60749 103 1"With Flnw 17,69 8.80 155,67 0.00 133863 101241201( 60749 103 1"With Finot 0-00 0.00 11.32 1166.99 133874 17.77 8.80 168.38 0.00 0100 0.00 11.38 167.78 -- 101241201 f 60749 103 1"With Flnef IS-81 9.80 165,53 0.00 Subtotal 0.00 0,01) 12.04 177.57 60749 I"With Fifl, 1,507.97 Ton -2,333.97 0-00 1,135.16 16,739.27 invoice Total ,1,607�7 Ton 13.270.14 2.333.97 0.00 1,135.16 16.739,27 Total InVOice---®- > 16,739,27 SHAKOPEE HOURS 7AM-430PM M-F DEDUCT DISCOUNT AMOUNT IF PAID WITHIN 10 DAYS OF INVOICE DATE 404.60 13AYPORT HOURS 7AM-430pM M-F Geyer Signal of St Cloud Inc 25112 22nd Ave Invoice St.Cloud NIN 56301 320-253-9005 Invoicek 1.06786 Fax: 320-654-6884 Date: 03/17/2017 Billed To: WIDMER CONSTRUCTION PrOjeCt, SHOREWOODTRUNK:WATERMAIN EXT 9455:CR 4,5 Client Job 16-04 MAPLE PLAIN MN 55350` Notes: QUANTITIES Terms: progress Payments Description Unit Mansurle, Quantity Unit Price Ext Price PORTABLE PRECAST BARRIER SF 100, $1,000.00 CRASH ATTE.NUATOR ASSEMBLY EA, 1 $2,400.Q0 $2,400.00 Please.snake checks payable to, CEYER SIGNAL OF ST.,+CLOt1D,•INC. Subtotal_ $4;200.00 Sales Tax: 0,00 Thank you for your prompt payment! Amount Due $4,200.00 Geyer Signal Of St Claud Inc 25112-22nd Ave St.Cloud,MN 56301 Invoice 320-253-9005 Fax: 320-654-6884 Invoi : 106938. Date; 03/22/2017 i11ee1 1®: 9455 WIDMER CONSTRUCTION Project: FiOREWOOD TRUNK WATERMAIN EXT 9455 CR 15 MAPLE PLAIN M Client JOb#N 55359 16-04 N®test QUANTITIES Terms: Progress'Payments Description Unit ®�salare ��u�nti Unit Price: RELOCATE PORTBALE PRECAST SARRIER` Ext Price RELOCATE CRASH ATTENUATOR ASSEMBLY FT 100' $5A0 EA. 1 $500.00 $500;00 $500,00 Please make checks payable t®: GEYER.SIGNAL OF ST.CLOUD;ZINC'. Subtotal: X1;000.00 Thank you for your prompt payment! Sales Tax: 0.00 Amount Due $1,000.00