17-087CITY OF SHOREWOOD
RESOLUTION NO. 17 -087
A RESOLUTION APPROVING CHANGE ORDER NO 1
FOR THE 2017 PAVEMENT RECLAMATION PROJECT
(HOWARDS POINT ROAD, KATHLEEN COURT, OAK RIDGE CIRCLE,
AND SUMMIT AVENUE)
CITY PROJECT 17 -13
WHEREAS, the City of Shorewood City of Shorewood Council awarded
the contract for the 2017 Pavement Reclamation Project (Howards Point Road, Kathleen
Court, Oak Ridge Circle, and Summit Avenue), City Project 17 -13, on September 11,
2017; and
WHEREAS, Change Order No. 1 is necessary to construct the improvements and
associated work to accommodate construction delays due to weather, permitting, utility
relocation, and reclamation subcontractor scheduling; and
WHEREAS, Change Order No. 1 will extend the project completion date to May
31, 2018, from the original contract completion date of November 10, 2017. Change
Order No. 1 does not increase the contract amount.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Shorewood, Minnesota:
1. Change Order No. 1 is approved, extending the contract completion date
to May 31, 2018.
ADOPTED BY THE CITY COUNCIL OF THE CITY OF SHOREWOOD
this 23rd day of October, 2017.
ATTEST:
Sandie Thone, City Clerk