18-076RESOLUTION NO. 18 - 076
A RESOLUTION APPROVING CHANGE ORDER NO 4
FOR THE 2017 PAVEMENT RECLAMATION PROJECT
(HOWARDS POINT ROAD, KATHLEEN COURT, OAK RIDGE CIRCLE,
AND SUMMIT AVENUE)
CITY PROJECT 17 -13
WHEREAS, the City of Shorewood City of Shorewood Council awarded
the contract for the 2017 Pavement Reclamation Project (Howards Point Road, Kathleen
Court, Oak Ridge Circle, and Summit Avenue), City Project 17 -13, on September 11,
2017;and
WHEREAS, Change Orders No. 1, 2 and 3 were necessary to construct the
improvements and associated work previously recommended by staff and approved by the
City Council; and
WHEREAS, Change Orders No. 1, 2 and 3 increased the project construction
costs in the amount of $15,055.95, to $825,980.55.; and
WHEREAS, Change Order 4 is necessary to address drainage concerns and
facilitate construction operations within the project corridor; and
WHEREAS, Change Order 4 will increase the project construction costs in the
amount of $16,595.34 to $842,575.89.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of
Shorewood as follows:
1. Change Order 4 in the total amount of $16,595.34 is hereby approved.
ADOPTED BY THE CITY COUNCIL OF THE CITY OF SHOREWOOD
this 13th day of August, 2018.
ATTEST:
Sandie Thone, City Clerk