Loading...
10_2_2018 Construction UpdateC Riviera Lane, Shorewood Lane, and Mann Lane Street and Utility Improvement Project CITY of Construction Update #10 SHOREWOOD Current Events The Contractor will continue with watermain construction along Riviera Lane throughout the week (week of October 15t) including installation of water services. Extension of the newly installed watermain along Yellowstone Trail to Riviera Lane will require the intersection to be closed (Yellowstone Trail traffic will have access through the intersection but access to and from Riviera Lane will be closed). The closure is anticipated to begin late afternoon Tuesday, October 2, 2018 and continue through Wednesday, October 3, 2018, weather permitting. Residents along Riviera Lane will have access to Riviera Lane before 7:00 a.m. and after 7:00 p.m. Monday through Friday. Throughout working hours, residents can park their vehicle(s) on Yellowstone Trail. Residents should anticipate parking their vehicles on Yellowstone Trail during working hours for the next three weeks, weather permitting. The Contractor is anticipated to complete bituminous base paving along Shorewood Lane tomorrow, Wednesday, October 3, 2018, weather permitting. Future Events The Contractor is anticipated to continue watermain and water service installation and begin storm sewer construction along Riviera Lane next week (week of October 8, 2018). The above schedule is tentative and is subject to change due to weather orscheduling conflicts. The City of Shorewood strongly encourages all residents and property owners to use the City website for construction activity updates, and to sign up for construction activity email, text, or Facebook messages. The website is located at http: / /www.ci.shorewood.mn.us Tips of the Week • Please observe posted detour and warning signs. • Please do not park vehicles on streets under construction. • Slow down and watch for uneven surfaces. • Stay alert! Watch for signs, equipment, and workers • Please remind children to stay away from the construction site, equipment, and stockpiles of materials. • Access through the site may change throughout the day as construction progresses; your patience is appreciated. Proiect Contacts Onsite Project Rep: Matt Havlik (612) 246 -9347 Project Manager. Katie Koscielak (612) 282 -3641 City Engineer. Alyson Fauske (952) 960 -7910