Loading...
10-17-2018 Road Construction Update Riviera Lane, Shorewood Lane, and Mann Lane Street and Utility Improvement Project Construction Update #13 Current Events th The Contractor has completed the remaining water service installation along Riviera Lane this week (week of October 15) and has begun excavating and constructing the roadway. Remaining storm sewer crossings will be installed as the sand section is constructed along the roadway. Installation of storm sewer crossings may cause intermittent access delays during construction. Residents are encouraged to continue parking on Yellowstone Trail. th The Contractor is anticipated to continue construction operations on Saturday, October 20, weather permitting. Future Events The Contractor is anticipated to continue excavating and constructing Riviera Lane up to and including the aggregate nd surface early next week (week of October 22) with the installation of concrete curb and gutter anticipated mid-week. The overhead utilities along Mann Lane are anticipated to be relocated to the new poles next week. Following the relocation of the overhead utilities, the Contractor is anticipated to begin pavement removals, excavation of the existing subgrade, and construction of the roadway, weather permitting. The above schedule is tentative and is subject to change due to weather or scheduling conflicts. The City of Shorewood strongly encourages all residents and property owners to use the City website for construction activity updates, and to sign up for construction activity email, text, or Facebook messages. The website is located at http://www.ci.shorewood.mn.us Tips of the Week  Please observe posted detour and warning signs.  Please do not park vehicles on streets under construction.  Slow down and watch for uneven surfaces.  Stay alert! Watch for signs, equipment, and workers  Please remind children to stay away from the construction site, equipment, and stockpiles of materials.  Access through the site may change throughout the day as construction progresses; your patience is appreciated. Project Contacts Onsite Project Rep: Matt Havlik (612) 246-9347 Project Manager: Katie Koscielak (612) 282-3641 City Engineer: Alyson Fauske (952) 960-7910