Fully signed PV1Pay Voucher CITY OF SHOREWOOD 5755 Country Club Road Shorewood, MN 55331 -8926 Project R- 011854 -000 - SHOR - 2018 Pavement Marking Project Pay Voucher No. 1 Contractor: Sir Lines -A -Lot 2400 E 26th Street Minneapolis, MN 55406 Contract Amounts Original Contract Contract Changes Revised Contract Work Certified To Date Contract No. Vendor No. N/A For Period: 7/23/201 8 - 8/31/2018 Warrant # Date Funds Encumbered $28,546.70 Original $0.00 Additional $28,546.70 Total Base Bid Items $12,284.19 Backsheet $0.00 Change Order $0.00 Supplemental Agreement $0.00 Work Order $0.00 Material On Hand $0.00 Total $12,284.19 Page I of 3 $28,546.70 N/A $28,546.70 This is to certify that the items of work shown in this certificate of Pay Voucher have been actually furnished for the work comprising the above mentioned projects in accordance with the plans and specifications heretofore approved. Approved By Approved By Sir Lines_ -A -Lot roject Cngi{{neer scc \ Contractor t Date Date Approved By Work Certified Work Less Less Amount Paid Total This Pay Certified Amount Previous This Pay Amount Voucher To Date Retained Payments Voucher Paid To Date R- 011854- $12,284.19 $12,284.19 $614.21 $0.00 $11,669.98 $11,669.98 000 Percent Retained: 5.0000% Percent Complete: 43.0319% Amount Paid This Pay VoucherT $11,669.96 This is to certify that the items of work shown in this certificate of Pay Voucher have been actually furnished for the work comprising the above mentioned projects in accordance with the plans and specifications heretofore approved. Approved By Approved By Sir Lines_ -A -Lot roject Cngi{{neer scc \ Contractor t Date Date Approved By Pay Voucher Page 2 of 3 CITY OF SHOREWOOD 5755 Country Club Road Shorewood, MN 55331 -8926 Project No. R- 011854 -000 Pay Voucher No. 1 R- 011854 -000 Payment Summary No. From Date To Date Work Certified Amount Retained Amount Paid Per Pay Voucher Per Pay Voucher Per Pay Voucher 1 07/23/2018 08/31/2018 $12,284.19 $614.21 $11,669.98 Totals: $12,284.19 $614.21 $11,669.98 R- 011854 -000 Fundina Cateaory Resort Funding Work Less Less Amount Paid Total Category Certified Amount Previous This Amount Paid No. To Date Retained Payments Pay Voucher To Date UNF 12,284.19 614.21 0.00 11,669.98 11,669.98 Totals: $12,284.19 $614.21 $0.00 $11,669.98 $11,669.98 R- 011854 -000 Fundina Source Resort Accounting Funding Amount Paid Revised Funds Paid To No. Source This Contract Encumbered Contractor Pay Voucher Amount To Date To Date UNF Unfunded 11,669.98 28,546.70 28,546.70 11,669.98 Totals: $11,669.98 $28,546.70 $28,546.70 $11,669.98 Pay Voucher Page 3 of 3 CITY OF SHOREWOOD 5755 Country Club Road Shorewood, MN 55331 -8926 Project No. R- 011854 -000 Pav Voucher No. 1 R- 011854 -000 Project Material Status Quantity Amount Line Item Description Units Unit Contract This This Quantity Amount Price Quantity Pay Pay To Date To Date Voucher Voucher SCHEDULE A - CITY OF SHOREWOOD ROADWAY PAVEMENT MARKINGS 1 2021.501 MOBILIZATION LS $3,000.00 1 0.75 $2,250.00 0.75 $2,250.00 2 2582.518 PAVT MSSG S F $3.60 800 210 $756.00 210 $756.00 PAINT 3 2582.503 4" SOLID LINE L F $0.09 93500 76491 $6,884.19 76491 $6,884.19 PAINT 4 2582.503 12" SOLID LINE L F $2.40 700 0 $0.00 0 $0.00 PAINT 5 2582.503 24" SOLID LINE L F $3.60 700 449 $1,616.40 449 $1,616.40 PAINT 6 2582.503 4" BROKEN L F $0.09 130 0 $0.00 0 $0.00 LINE PAINT 7 2582.503 4" DBLE SOLID L F $0.18 22000 0 $0.00 0 $0.00 LINE PAINT 8 2582.518 CROSSWALK SF $2.70 1500 288 $777.60 288 $777.60 PAINT Totals For Section SCHEDULE A - CITY OF SHOREWOOD $12,284.19 $12,284.19 ROADWAY PAVEMENT MARKINGS: SCHEDULE B. - CITY OF SHOREWOOD PARKING LOT IMPROVEMENTS 9 2021.501 MOBILIZATION LS $750.00 1 0 $0.00 0 $0.00 10 2582.518 PAVT MSSG S F $9.50 40 0 $0.00 0 $0.00 PAINT 11 2582.503 4" SOLID LINE L F $0.60 1500 0 $0.00 0 $0.00 PAINT Totals For SCHEDULE B. - CITY OF SHOREWOOD PARKING $0.00 $0.00 LOT IMPROVEMENTS: Project Totals: $12,284.19 $12,284.19