Change Order No. 3CHANGE ORDER NO.3
2018 STREET AND UTILITY IMPROVEMENT PROJECT January 9, 2019
CITY OF SHOREWOOD, MN
WSB PROJECT NO. 2925-24
OWNER:
CITY OF SHOREWOOD
5755 COUNTRY CLUB ROAD
SHOREWOOD, MN 55331
CONTRACTOR:
MIDWEST CIVIL CONSTRUCTORS, LLC
100 S FULLER ST, SUITE 130
SHAKOPEE, MN 55379
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
ALL LABOR, MATERIALS, AND EQUIPMENT NECESSARY TO COMPLETE THE FOLLOWING ITEMS AS DIRECTED BY THE CITY ENGINEER:
REMOVAL OF BURIED DEBRIS WITHIN RIVIERA LANE CUL-DE-SAC
PRECONSTRUCTION SURVEY AT 6025 RIVIERA LANE
MUCK EXCAVATION, BYPASS PUMPING AND DRAIN TILE REPAIR NECCESSARY DUE TO THE UNKNOWN DRAIN TILE CROSSING ON MANN LANE
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR
FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE: $1,708,509.00 ORIGINAL CONTRACT TIME: 6/15/2019
PREVIOUS CHANGE ORDERS: $10,801.73 NET CHANGE FROM PREVIOUS CHANGE ORDERS: N/A
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER: $1,719,310.73 CONTRACT TIME PRIOR TO THIS CHANGE ORDER: 6/15/2019
NET INCREASE OF THIS CHANGE ORDER: $21,534.65 NET INCREASE WITH CHANGE ORDER: NIA
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS: $1,740,845.38 CONTRACT TIME WITH APPROVED CHANGE ORDERS 6115/2019
APPROVE¢$Y:
�ACYSOM FAOSKE, P8, PROJECT MA ER
WSB & ASSOCIATES, INC.
ENGINEER
I
APPROVED BY:
CON ACTOR SIG ATURE
MIDWEST CIVIL CONSTRUCTORS, LLC,
CONTRACTOR
TY ADMINISTRATOR
DATE
K:102925-240lAdmintConstruction AdminiChengo OrdorstChengs Order No. 31Chenga Order No. 3CO-3
CHANGE ORDER NO.3 DETAIL
2018 STREET AND UTILITY IMPROVEMENT PROJECT January 9, 2019
CITY OF SHOREWOOD, MN
WSB PROJECT NO. 2925-24
ADDED ITEMS
Item No. Mat. No. Descri
140 2105.607 EXCAVATION SPECIAL
141 2011.601 CONSTRUCTION SURVEYING
142 2105.507 MUCK EXCAVATION
TOTAL ADDED ITEMS CHANGE ORDER NO. 3
Unit
Qty
Price
Extended Amount
L S
1
$11,465.35
$11,465.35
L S
1
$550.00
$550.00
C Y
90
$105.77
$9,519.30
$21,534.65
TOTAL ADJUSTMENT TO ORIGINAL CONTRACT AMOUNT $21,534.65
K:102925- 24014dminIConstruction AdminlChange OrderslChange Order No. 31Change Order No. 3CO3 Detail