AppendixB Western Shorewood Stormwater Management Plan: Preferred Alternatives ReviewWestern Shorewood
Stormwater Management Plan:
Preferred Alternatives Review
Jen Koehler, PE
12/18/2019
BARR
1
Scope
• Survey of key areas
• Review and revisions of existing XP -SWMM model
• Develop existing conditions P8 model
• Reevaluation of recommended alternatives
— Looking at alternatives feasibility
— Considering feedback from MCWD
• Further evaluation and development of preferred concept
• Did not include efforts that would be complete during final
design /permitting: wetland delineation, tree survey, design survey
2
■
BARR
12/18/2019
1
Background
■ Numerous areas with drainage issues in Western
Shorewood
—Area 1: Shorewood Oaks*
— Area 2: Strawberry Lane*
— Area 3: Freeman Park*
— Area 4: Beverly Drive
— Area 5: Grant Lorenz Channel*
— Area 6: Noble Road — No preferred alternative at this time
3
M
BARB
12/18/2019
4
2
12/18/2019
to
r
ro
f
W .3 JA "i t
I
n
..a
x �
drtions
tl� ��.r }
9C
Area 1: Shorewood Oaks Sump System
Issues
• Current system designed in 1985
• Sumps on —50 homes connect to
sump drain system (6" PVC) that
connects at the storm sewer
manhole at the low point on
Shorewood Oaks
— invert 962.52 ft MSL
— System primarily below 964.0 ft MSL
• Storm system to Freeman Park
surcharges during rain events and
results in flooding residences during
intense events
— No GW issues in between events
per comment from resident
7
Freeman Park
connection
low
point /sump
connection
BARR
Area 1: Shorewood Oaks Sump System
Preferred Solutions
1
L _ o
rrY
Etta`
I
• Collect for Reuse - option
eliminated
• S01: Abandon and Daylight
• S02: Separate System and
Gravity Drain to North of
Regional Trail
BARR
12/18/2019
M
Area 1: Shorewood Oaks Sump System
Preferred Solutions
■ SO1: Abandon sump system and require private
property owners to daylight sump pump /foundation
drain discharges at surface
— Daylight —50 homes
— Line /Fill sump system piping and bulkhead at storm
manhole?
— Some concern by city in oversaturating soils in right of way
and under roads with sump discharge
X
Area 1: Shorewood Oaks Sump System
Preferred Solutions
■ SO2: Separate the sump system from the primary storm
system and drain to north of regional trail (Smithtown
Pond)
— Required directional drilling 1600 ft of 8" HDPE to north of
regional trail
— US invert: 962.5, DS invert: 956.6 (0.35% slope)
10
M
BARB
M
BARR
12/18/2019
5
Area 1: Shorewood Oaks Sump System
Costs
S01: Abandon and Daylight
S02: Separate system and gravity drain to north of
regional trail
*Costs include Engineering, Design, and Permitting (25 %)
Based on limited design, uncertainty in cost -30% to +50%
11
$190,000
$580,000
M
BARB
12/18/2019
12
0
Area 2: Strawberry Lane - North of Trail
Issues
• Flat topography /limited
drainage
— No issues with flooded
structures
• Existing draintile system along
ditches that connects to storm
that drains to Pebble Brook
— Rate of drainage limited by
infiltration through ditch
• Existing erosion in Pebble
Brook Creek channel
13
Area 2: Strawberry Lane
Preferred Solutions
y l
4'
14
3ARR
Installation of linear box culvert under
proposed trail & stabilization of Pebble Brook —
option eliminated
SL -1: Storm sewer along Strawberry Lane north
to Smithtown, eliminate Strawberry Lane
discharge to Pebble Brook Creek
SL -2: Storm sewer along Strawberry Lane north
to Smithtown, split flows from Storm sewer to
the north and Pebble Brook Creek
e-
12/18/2019
7
Area 2: Strawberry Lane
Preferred Solutions
■ SL -1: Installation of storm sewer under proposed trail
routed north to Smithtown Road to the proposed
Smithtown Pond — Diversions of all Strawberry Lane
runoff away from Pebble Brook Creek
— SL -1a: Reduce 100 -year = 48" RCP
— SL -1 b: Maintain 100 -year = 18 "RCP
15
Area 2: Strawberry Lane
Preferred Solutions
■ SL -2: Installation of storm sewer under proposed trail
routed north to Smithtown Road to the proposed
Smithtown Pond — Split Strawberry Lane runoff between
storm sewer and Pebble Brook Creek, Stabilization along
Pebble Brook Creek
— SL -2a: Reduce 100 -year = 48" RCP
— SL -2b: Maintain 100 -year — 18 "RCP
16
BARR
BARR
12/18/2019
17
Area 2: Strawberry Lane
Preferred Solutions
■ Directional Drilling Considerations
— Any obstructions (gravel, till, cobbles etc.) can be challenging
— We have experience directional drilling 42" pipe, typically smaller is
easier /cheaper
— Need at least 10 feet of separation from edge of existing utility and
edge of hole (hole is 1.5x diameter of pipe)
— Experienced contractors (especially as you move up in
size /complexity) are more expensive but likely worth the cost
— Unit costs are all over the board
Area 2: Strawberry Lane
Preferred Solutions
IN MATrM
_
ST
K
TRIPE C-ROS
4' TH ICX INSULATION
096
_
I gI
-
OA
3rl 04
"r
-
y (; PVC BEND
C
o
1 IN STALL
SALVAG ED S IGN \ J
I FI
A`
CONSTRUCTION LIAR TS
a�
I
'S _
1. SEE SHEETS CROSS SECTIONS FOR DRIVEWAI REPLACe NE
2. SAWCHT EXISTING DITUMINEUS PAV EMENT ( Pl1LL DEPTH)
3- MAIL0OX TO BE RELOCATED.
9. SIGNS TO BE RELOCATEO,
r
5. INSTALL 9° TOPSOIL A SEED.
&. CATCH BASIN TOP OF CASTINGS ARE DEPRESSED
(NEENAH R- 3G67 -V OR APPROVED EOUAL].
1. THE CONTRACTOR SHALL SALVAGE AND STOCK
PILE TUP
18
CIS
x
0
0
a
N
M
BARB
.SNTOX �MSV�pS,oN JOp 'e. SNNO� `N
LOT S, BLOCK 1
PEBBLE BROOK ADDN I
BARR
12/18/2019
a
Area 2: Strawberry Lane
Impacts & Costs
Existing Conditio 970.6
SL1a:Storm Sewer & 970.2
Diversion (No Channel
Stabilization) — Reduce 100 -
year (48 ")
SL1b: Storm Sewer & 970.6
Diversion (No Channel
Stabilization) — MaintaA'N
year (18 ")
SL2a: Storm Sewer, Split Flows 970.1
& Channel Stabilization —
Reduce 100-year (48")
969.1 2/7
�-
968.9 0/3 0.7 $2,110,000
969.1 1 /3 0.7 $1,080,000
968.8 0/3 0.7 $2,180,000
Storm Sewer, Split 1 /3 $1,150,000
Flows &Channel Stabilization
— Maintain 100 -year (18 ") =ME T�
*Costs include Engineering, Design, and Permitting (25 %)
Based on limited design, uncertainty in cost -30% to +50%
19
BARR
Area 2: Pebble Brook Peak Flows
Potential Solution Atlas 14 1 -Year, 24- Atlas 14 2 -Year, Atlas 14 10 -Year, Atlas 14 100 -
Hour Peak Flow (cfs) 24 -Hour Peak 24 -Hour Peak Year, 24 -Hour
Flow (cfs) Flow (cfs) Peak Flow (cfs)
Existing Conditions 5.7 • : 26.4 135.0
Storm : Diversion
• Channel Stabilization)
Storm • Flows,
& Channel Stabilization
BARR
20
12/18/2019
10
12/18/2019
21
Area 3: Freeman Park
Issues
• Outlet structure flagged as critical during
Hennepin County Regional Railroad Authority
Stormwater Infrastructure Qualitative Failure
Risk Assessment (Feb 2018)
— 48" Pipe with joint separation
• Flood elevation surcharges Shorewood Oaks
system and has caused flooding of sump
systems /private residences
• Debris and plugging ongoing maintenance
issues
• Downstream erosion issues along Grant
Lorenz channel
• Standing water in ball fields
• Groundwater high in area (water table within
a few feet of ground surface)
22
M
BARR
11
Area 3: Freeman Park
Issues
Icy^ � SfP cwl rn
P1K tKmc
-mvsue or � -i.
3 a
FP1 R pl and low 1111W IM Fl------ N . n �. ..
P"nnWA
,J
", SS
of �a \STi
tt�
\
cyFF'➢
wV.9S95
y0
��
I
�� QO
57UCTLU 2E
w
BARB
23
Area 3: Freeman Park
Preferred Alternative
24
12/18/2019
12
3 a
FP1 R pl and low 1111W IM Fl------ N . n �. ..
I
�� QO
-
���� « °,� � �: �. ..
i'-\: � �� •r, �'1 ':r�r BAR
24
12/18/2019
12
25
Area 3: Freeman Park
Preferred Alternative
• FP1: Lower outlet elevation
to 957.5
— Will require a small amount of
grading/ excavation at inlet
• Conceptual design that
minimizes maintenance
— Bollards to prevent movement
of large debris to trash rack
— Oversized inlet with trash rack
— Overflow at 10 -year event
Area 3: Freeman Park
Impacts & Costs
Monditio� A�
FP1: Lower Outlet to 957.5 969.5 0/0 N/A
More significant peak elevation reductions during more frequent events (1 -yr, 2 -year)
*Costs include Engineering, Design, and Permitting (25 %)
Based on limited design, uncertainty in cost -30% to +50%
26
$86,000
BARR
BARR
12/18/2019
13
12/18/2019
PAN
Area 5: Grant Lorenz Channe
Issues
■ High flows /velocities resulting in erosion
and sediment transport
— Velocities exceed 3 -4 fps in several sections of the
channel, likely contributing to erosion without well
established vegetation or other stabilization
— Downstream of Grant Lorenz Road, the Channel is
incised and disconnected from the floodplain
— Shear Stress typically exceeds vegetation
thresholds during larger events
■ Overtopping driveways and destroying
culverts
28
14
Area 5: Grant Lorenz Channe
Issues
PAS]
Area 5: Grant Lorenz Channe
Issues
30
m
BARB
m
BARR
12/18/2019
15
Area 5: Grant Lorenz Channe
Preferred Solution
■ GL1: Smithtown Pond (Maximized) with —
extended detention outlet 1.
— 15" x 18" notch weir @ 952.0 ft MSL C
— 6' Weir @ 953.5 ft MSL
— Rate /Flood Control and WQ Treatment
• 1.5 acre -ft of additional WQ treatment volume
• 13.7 acre -ft of Additional Flood Control
Volume-
�
— Possible IESF along Pond (-10'x250')
I
J
■ Stabilization along Channel
31
Area 5: Grant Lorenz Channe
Preferred Solutions
■ Reconfiguration of culvert
crossing on Grant Lorenz
Road
■ Stabilization along channel
—Constructed Riffles
—Targeted rip rap /hard armor
—Targeted grading and
vegetation reestablishment
32
BARR
12/18/2019
16
33
Area 5: Grant Lorenz Channe
Potential Solutions
Assumptions:
City can obtain drainage and construction access aagreements
Access from east side of channel – limit impacts on home side of channel -
Limited tree removal – remains shady, shade tolerant vegetation B =R
Area 5: Grant Lorenz Channel
Impacts - 100 -yr Flood Elevations
Grant Lorenz Channel
953.8
951.7 ( -2.1 ft) -2
Stabilization – G
Grant Lorenz Channel
953.7
951.2 ( -2.5 ft) 0
Stabilization – F
Grant Lorenz Channel
qwx�
948.6 ( -3.3 ft) -1
Stabilization – E
Grant Lorenz Channel
948.1
947.4 ( -0.7 ft) 0
Stabilization – D
Grant Lorenz Channel
941.5 ( -0.0 ft)
Stabilization – B
AM&
ML
Grant Lorenz Channel
938.1
937.9 ( -0.2 ft) -1
Stabilization –A
34
r 1
BARR
12/18/2019
17
Area 5: Grant Lorenz Channe
Impacts - Peak Flows
Grant Lorenz Channel
Stabilization — G
Grant Lorenz Channel
Stabilization — F
18.7; 21%
20.1; 34%
24.5; 21% 39.1; 40% 102.1; 50%
25.8; 37% 43.1; 51% 113.1; 51%
Grant z Channel
F9;
Stabilization
20.5; 38%
26.2; 41° 49%
Grant Lorenz Channel
Stabilization — D
20.7; 39%
26.4; 42% 52.8; 45% 130.8; 48%
Grant Lorenz Channel
Stabilization — B
20.7; 40%
26.5; 43% 54.9; 43% 146.5; 45%
Grant Lorenz Channel
Stabilization —A
21.6; 39%
27.7; 41% 56.5; 43% 151.0; 44%
35
Area 5: Grant Lorenz Channe
Impacts & Costs
Existing Conditions 956.6 1 /0
GL1a: Smithtown 956.6 1 /0
Pond (Maximized) w/
Extended Detention
& Channel
Stabilization
GL1 b: Smithtown 956.6
Pond (Maximized) w/
Extended Detention,
IESF, li Channel
Stabilization
*Costs include Engineering, Design, and Permitting (25 %)
Based on limited design, uncertainty in cost -30% to +50%
36
0.5
9.2
UNI
$3,580,000
BARR
12/18/2019
im
12/18/2019
[ell
Area 4: Beverly Drive Wetland
Issues
• High flood elevations on Beverly Drive wetland
• Potentially impacted homes
• Pipe is technically private except within right of way
along Cajed Lane
• Pipe is collapsed in low area north of Beverly and west
of Cajed — flooding back yards and cemetery
• Beverly wetland is mapped as wetland
— NWI: Freshwater Emergent wetland
— MCWD: Manage 1 Wetland
• Cajed low area also mapped as wetland
— MCWD: No Classification
— NWI: Freshwater Emergent wetland
38
19
Area 4: Beverly Drive Wetland
Issues
■ Survey of low opening at 951.56
NGVD29
— close to LiDAR estimate of 951.5
100 -yr WSE: 953.3
10 -yr WSE: 951.8
2 -yr WSE: 950.9
1 -yr WSE: 950.6
39
12/18/2019
Area 4: Beverly Drive Wetland
Impacts
Potential Solution Atlas 14 100-Year, Atlas 14100-Year, Atlas 14 100-Year, Potentially Planning Level Cost*
24-Hour Peak 24-Hour Peak 24-Hour Peak Impacted
Flood Elevation - Flood Elevation - Flood Elevation -
Wetland
Existing Conditions J� 953.3 949.0 932.4 1 / 2
131: Replace 8 ", Add 8" at 953.2 946.9 932.4 1/0 $580,000
Cajed Low Area
132: Upsize to 15 ", Ad 952.7 946.5 I 1/0 $640,000
12" at Cajed Low Are
133: Upsize to 24 ", Add 952.3 946.3 932.5 1/0 $750,000
12" at Cajed Low Area
134: Upsize to 24" & 952.0 946.3 932.5 1/0 $750,000
Lower to 948, Add 12" at
Cajed Low Area MINE- `
*Costs include Engineering, Design, and Permitting (25 %) B =R
Based on limited design, uncertainty in cost -30% to +50%
40
20
41
Area 4: Beverly Drive Wetland
Preferred Solution
■
131: Replace drainage system
from Beverly Drive and along
Cajed Lane, including
installation of inlet in low
area north of Beverly and
west of Cajed
— Assume directional drilling (8 ")
— Sanitary and watermain along
Cajed Lane — avoid conflict
Area 4: Beverly Drive Wetland
Impacts
12/18/2019
Existing Conditions 953.3 949.0 932.4 1 / 2
B1: Replace 8" at Beverly, 953.2 946.9 932.4 1/0 $580,000
Add 8" at Cajed Low
Area
*Costs include Engineering, Design, and Permitting (25 %) BARRR
Based on limited design, uncertainty in cost -30% to +50%
42
21
Western Shorewood - Preferred Concept Summary
Area 1:
Shorewood
S01: Daylight and Abandon
S01: $190,000
S01: Independent of other
Oaks
S02: Separate and Discharge North of
S02: $580,000
projects
Regional Trail
S02: After Smithtown Pond (due
_
111
to discharge elevation)
Area 2:
Strawberry
SL1: Storm Sewer North to Smithtown
SL1: $1,080,000
SL1: After Smithtown Pond
Lane
Road
SL2: $1,150,000
SL2: After Smithtown Pond
SL2: Storm Sewer North to Smithtown
Road, Split Flows & Channel Stabilization
Area 3:
Freeman
FP1: Lower outlet
FP1: $86,000
FP1: After Smithtown Pond (due
Park
i
i
i fro
discharge elevation) M
Area 4: Beverly BW1: Replace 8" at Beverly, Add 8" at
Drive Cajed Low Area
Area 5: Grant Lorenz GL1a: Smithtown Pond and Channel
Channel Stabilization
i GL1b: Smithtown Pond, IESF and Channel
Stabilization
Area 6: Noble Road N/A
*Costs include Engineering, Design, and Permitting (25 %)
Based on limited design, uncertainty in cost -30% to +50%
43
Next Steps
Total Cost
BW1: $580,000 Independent of other projects
GL1a: $3,580,000 Smithtown Pond (& IESF) should
G L 1 b: $3,640,000 be constructed prior to channel
ab'lization
N/A N/A
Finalize preferred alternative based on today's meeting Late December /Ear&aanuary 2020
Council work session regarding preferred alternative Mid January (January 13, 2020)
Pullen house presentingferred alternativ�muary 2020
Draft plan and review with City and MCWD staff Late January 2020
Finalize pl Vd February 2020
Present final plan to City Council Late February (February 24, 2020)
• Council work session - Format /length? Time? City will schedule?
• Public open house — week of January 20 -24? Format /length? Time? City will
schedule /advertise?
44
BARR
12/18/2019
22