WHEREAS, the Shorewood City Council awarded the contract for the Boulder Bridge Motor
Control Project, City Project 18 -01, on July 23rd, 2018, to AE2S Construction, LLC DBA
Electrical Installation and Maintenance (EIM); and
WHEREAS, Change Order 3 is necessary to facilitate requested changes to the water system;
and
WHEREAS, Change Order 3 will increase the project construction costs in the amount of
$2,997.42 to a revised Contract amount of $138,127.47, as documented in Exhibit A.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Shorewood as
follows:
1. Change Order 3 is hereby approved and as outlined in Exhibit A.
ADOPTED BY • OF OF •- ••r day of
March, 2019.
Sco Zerby, ayo