19-075CITY OF SHOREWOOD
COUNTY OF HENNEPIN
STATE OF MINNESOTA
RESOLUTION 19 -075
A RESOLUTION ACCEPTING FINAL IMPROVEMENTS AND
AUTHORIZING FINAL PAYMENT FOR THE
BOULDER BRIDGE MOTOR CONTROL CENTER PROJECT,
CITY PROJECT 18 -01
WHEREAS, on July 23, 2018, the Shorewood City Council awarded the contract for the
Boulder Bridge Motor Control Center Replacement Project, City Project 18 -01 to
Electrical Installation and Maintenance. Inc.; and
WHEREAS, the Contractor has completed the project work and has requested City
acceptance of the project and final payment for the work performed and documented to
date; and
WHEREAS, the Director of Public Works has made final inspection of the project and
recommends acceptance and final payment be made by the City.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
SHOREWOOD, MINNESOTA AS FOLLOWS:
1. The City hereby accepts the work completed, pursuant to said contract and
authorizes final payment to the Contractor.
2. All warranties shall commence as of the date of substantial completion, of
April 12, 2019.
Passed by the City Council of Shorewood, Minnesota this 12th day of August, 2019.
::s� "4v� Z��'
S C oJ,,11r by, Ma r
Attest: _
Sandie Thone, City Clerk