20-023z
RESOLUTION 20 -023
RESOLUTION PREPARE REPORT PRELIMINARY DESIGN
FOR THE MARY OUTLET PROJECT
PROJECT CITY 0.
WHEREAS, over the last 20 years the city has had to pump surface water out of a land
locked Mary Lake that does not have a natural drainage outlet. The last pumping effort
was from September 24, 2019 thru November 14, 2019 where water levels threatened
to damage private property; and
WHEREAS, the current Capital Improvement Plan (CIP) identifies improvements to
provide an outlet from a land locked Mary Lake in 2020; and
WHEREAS, staff has worked with Barr Engineering and associated permitting agencies
to review concept alternatives in which a recommended solution has been identified;
and
WHEREAS, the City Council as appointed Bolton & Menk as the City Engineer and will
prepare the feasibility report and preliminary design for the Mary Lake Outlet; and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
SHOREWOOD, MINNESOTA AS FOLLOWS:
1. The City Council of the City of Shorewood, Minnesota authorizes Bolton & Menk
to complete a feasibility report and preliminary design for the Mary Lake Outlet
project.
Passed by the City Council of Shorewood, Minnesota this 9t" day of March, 2020.
Sc erby, yor
A Te s t:
Sandie Thone, City Clerk