80-093
.
.
.
RESOLUTION NO. 93-;:.0
WHEREAS, pursuant to an advertisement for bids for the
improvement of real estate within Phase 1 of the plat
of Boulder Bridge Farm in the City of Shorewood, which project
has been designated Project 80 WTP-2, bids were received, opened
and tabulated according to law and the following bids were
received complying with the advertisement: B Alt t
ase erna e
$139,797.00 $8,219.00~
160,900.00 16,000.00
MacInerny, Inc.
Gridor Construction, Inc.
Lee Richert Plumbing &
Heating, Inc.
New Mech Company
Johnson Engineering Co.
A. & K. Construction, Inc. of
Stillwater, Minn.
138,200.00
160,230.00
163,400.00
137,905.00
28,200.00
22,200.00
29,500.00
21,960.00
and
WHEREAS, the engineer has reviewed the bids for accuracy and
has made his recommendation to the council to accept the base bid
and alternate bid of the lowest responsible bidder and it appears
that is the
lowest responsible bidder for the base bid and for the alternate
bid as a combination improvement of the Boulder Bridge Farm
Phase 1, Project 80 WTP-2, for construction of pump house and
appurtenant work, having submitted a bid of
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF SHOREWOOD:
1. The Mayor and the Clerk/Administrator are hereby authorized
and directed to enter into the contract, the form of which has been
attached to the bid specifications, with
in the name of the City of Shorewood for improve-
ment of Boulder Bri.dge Farm, Phase 1, project 80 WTP-2, being for
the installation of pump house and appurtenant work, all according
to the plan:3 and specifications heretofore approved by this city
council and on file in the office of the City Clerk.
2. The City Clerk is hereby authorized to return forthwith
to all bidders the deposits made with their bids,. except that the
deposit of the successful bidder and the next lowest bidder shall
be retained until a contract has been filed.
Adopted by the city council this ~day of J)~embeY , 1980
On the resolution being called, there were
ayes
nays