CITY OF SHOREWOOD
RESOLUTION NO. 06- 066
A RESOLUTION APPROVING A CHANGE ORDER 3
FOR THE COUNTY STATE AID HIGHWAY 19 - SMITHTOWN ROAD
INTERSECTION IMPROVEMENT PROJECT,
CITY PROJECT NO. 97-07
WHEREAS, on November 8, 2004, the City of Shorewood entered into a
contract for construction with Eureka Construction, Inc. for the County State Aid
Highway 19 - Smithtown Road Intersection Improvement Project, City Project No. 97-
07; and
WHEREAS, WSB and Associates has prepared Change Order 3 attached hereto
as Exhibit A, for additional work outside of the original contract; and
WHEREAS, the Director of Public Works has reviewed said Change Order and
found it to be cost effective for the project.
NOW, THEREFORE BE IT RESOLVED by the City of Shorewood to approve
Change Order Number 3 with Eureka Construction, Inc, that incorporates services
outlined in Change Order 3, attached hereto as Exhibit A.
ADOPTED by the City Council of the City of shor. 70 d.....,thiS 29th day of
August, 2006. .
~:;L---
ATTEST: WOODY LOVE, MAYOR
. A WSON, CITY ADMINISTRATOR/CLERK
Mn/DOT TP-2460-0 112-92)(Revised _Hennepin _2004)
Hennepin County Public Works
Transportation Department
CHANGE ORDER # 3
Contractor:
Address:
Eureka Construction Inc.
8500 21 Oth Street West
Suite 130
Lakeville, MN 55044
State Project No.: 27-619-18
Federal Project No.:
Contract No.: 9821
Location:
CSAH 19/5mithtown Road Intersection
Sta. 104+00 to Sta. 128+00
In accordance with the terms of this Contract, you are hereby authorized and instructed to perform the Work as altered by the
following provisions.
Due to observed field conditions of the inplace subgrade, the Engineer authorized additional common excavation to
remove unsuitable material within the roadway core. Additional select granular borrow was required to be placed under
the temporary widening area to support traffic due to wet subsoil conditions. The following contract plan quantity items
will be increased as shown below:
G N 1
roup o.
Item No. Description Unit Unit Price Quantity Amount
2105501/00010 Common Excavation (P) CU.Yd. $7.50 2726.94 $20,452.05
2105.522/00030 Select Granular Borrow (CV) (P) Cu. Yd. $11.00 811.72 $8,928.92
TOTAL $29,380.97
Cost Distribution: S.A.P. 27-619-18 = 100% Hennepin County
Total Increase of Change Order No.3
$29,380.97
CHANGE IN CONTRACT TIME
Due to this change the Contract Time:
a.
Is increased ( ) by _ Working Days
Is decreased ( ) by _ Working Days
I~ued By: ;JiI 1/42 e/?jo6
f Date
Construction Project Engineer
Is increased () by _ Calendar Days
Is decreased ( ) by _ Calendar Days
Approved by:
City of Shore wood Engineer
Date
b. Is not changed ( x )
c. May be revised if the work affected
the controlling operation ( )
Approved By:
Hennepin County Construction Engineer
----
Accepted By: ~~
Contractor's Authorized Representative
Date
0/3/06
Date
File: CE, PE, FO, Contractor
SHEET 1 OF ]
F:',WPWINI1388-01\CHANGE OM
Exhibit A