Loading...
06-066 CITY OF SHOREWOOD RESOLUTION NO. 06- 066 A RESOLUTION APPROVING A CHANGE ORDER 3 FOR THE COUNTY STATE AID HIGHWAY 19 - SMITHTOWN ROAD INTERSECTION IMPROVEMENT PROJECT, CITY PROJECT NO. 97-07 WHEREAS, on November 8, 2004, the City of Shorewood entered into a contract for construction with Eureka Construction, Inc. for the County State Aid Highway 19 - Smithtown Road Intersection Improvement Project, City Project No. 97- 07; and WHEREAS, WSB and Associates has prepared Change Order 3 attached hereto as Exhibit A, for additional work outside of the original contract; and WHEREAS, the Director of Public Works has reviewed said Change Order and found it to be cost effective for the project. NOW, THEREFORE BE IT RESOLVED by the City of Shorewood to approve Change Order Number 3 with Eureka Construction, Inc, that incorporates services outlined in Change Order 3, attached hereto as Exhibit A. ADOPTED by the City Council of the City of shor. 70 d.....,thiS 29th day of August, 2006. . ~:;L--- ATTEST: WOODY LOVE, MAYOR . A WSON, CITY ADMINISTRATOR/CLERK Mn/DOT TP-2460-0 112-92)(Revised _Hennepin _2004) Hennepin County Public Works Transportation Department CHANGE ORDER # 3 Contractor: Address: Eureka Construction Inc. 8500 21 Oth Street West Suite 130 Lakeville, MN 55044 State Project No.: 27-619-18 Federal Project No.: Contract No.: 9821 Location: CSAH 19/5mithtown Road Intersection Sta. 104+00 to Sta. 128+00 In accordance with the terms of this Contract, you are hereby authorized and instructed to perform the Work as altered by the following provisions. Due to observed field conditions of the inplace subgrade, the Engineer authorized additional common excavation to remove unsuitable material within the roadway core. Additional select granular borrow was required to be placed under the temporary widening area to support traffic due to wet subsoil conditions. The following contract plan quantity items will be increased as shown below: G N 1 roup o. Item No. Description Unit Unit Price Quantity Amount 2105501/00010 Common Excavation (P) CU.Yd. $7.50 2726.94 $20,452.05 2105.522/00030 Select Granular Borrow (CV) (P) Cu. Yd. $11.00 811.72 $8,928.92 TOTAL $29,380.97 Cost Distribution: S.A.P. 27-619-18 = 100% Hennepin County Total Increase of Change Order No.3 $29,380.97 CHANGE IN CONTRACT TIME Due to this change the Contract Time: a. Is increased ( ) by _ Working Days Is decreased ( ) by _ Working Days I~ued By: ;JiI 1/42 e/?jo6 f Date Construction Project Engineer Is increased () by _ Calendar Days Is decreased ( ) by _ Calendar Days Approved by: City of Shore wood Engineer Date b. Is not changed ( x ) c. May be revised if the work affected the controlling operation ( ) Approved By: Hennepin County Construction Engineer ---- Accepted By: ~~ Contractor's Authorized Representative Date 0/3/06 Date File: CE, PE, FO, Contractor SHEET 1 OF ] F:',WPWINI1388-01\CHANGE OM Exhibit A