06-065
CITY OF SHOREWOOD
RESOLUTION NO. 06- 065
A RESOLUTION APPROVING A CHANGE ORDER 2
FOR THE COUNTY STATE AID HIGHWAY 19 - SMITHTOWN ROAD
INTERSECTION IMPROVEMENT PROJECT,
CITY PROJECT NO. 97-07
WHEREAS, on November 8, 2004, the City of Shorewood entered into a
contract for construction with Eureka Construction, Inc. for the County State Aid
Highway 19 - Smithtown Road Intersection Improvement Project, City Project No. 97-
07; and
WHEREAS, WSB and Associates has prepared Change Order 2 attached hereto
as Exhibit A, for additional work outside of the original contract; and
WHEREAS, the Director of Public Works has reviewed said Change Order and
found it to be cost effective for the project.
NOW, THEREFORE BE IT RESOLVED by the City of Shorewood to approve
Change Order Number 2 with Eureka Construction, Inc, that incorporates services
outlined in Change Order 2, attached hereto as Exhibit A.
ADOPTED by the City Council ofthe City of
August, 2006.
ATTEST: WOODY LOVE, MAYOR
C D WSON, CITY ADMINISTRATOR/CLERK
Mn/DUT TP-2460-0 112-92 )(Revised _Hennepin _ 2004)
Hennepin County Public Works
Transportation" :t)epartment
CHANGE ORDER # 2
Contractor:
Address:
Eureka Construction Inc.
8500 210th Street West
Suite 130
Lakeville, MN 55044
State Project No.: 27-619-18
Federal Project No.:
Contract No.: 9821
Location:
CSAH 19/5mithtown Road Intersection
Wall No.1 Sta. 104+90 to Sta. 108+60 LT
Wall No.2 Sta. 116+65 to Sta. 119+10 LT
Wall No.3 Sta. 119+00 to Sta. 119+45 RT
Wall No.4 Sta.23+56 to Sta. 24+82 LT
Wall No.5 Sta. 23+19 to Sta. 24+53 RT
In accordance with the tenns of this Contract, you are hereby authorized and instructed to perform the Work as altered by the
following provisions.
Due to field modifications for retaining Wall No.1, 2,3,4, and 5, as authorized by the Engineer, concrete for the footing
and stem, along with reinforcement plan quantities and architectural texture and color system, will be increased as shown
below:
Group No. 1
Item No. Description Unit Unit Price Quantity Amount
2401.501/01143 Structural Concrete (lA43) (P) CU.Yd. $420.00 22.9 $9,618.00
2401.501/03643 Structural Concrete 3Y43(P) Cu.Yd. $445.00 16.95 $7,542.75
2401.541/00010 Reinforcement Bars (P) Pound $1.05 664.50 $697.73
2401.541/00011 Reinforcement Bars (Epoxy Coated) (P) Pound $1.35 2589.5 $3,495.83
2411.511/00013 Structural Excavation Class U (P) Cu. Yd. $9.00 30.5 $274.50
TOTAL $21,628.81
Cost Distribution: S.A.P. 27-619-18 = 100% Hennepin County
Group No.2
Item No. Description Unit Unit Price Quantity Amount
2411.618/00530 Architectural Concrete Texture Sq.Ft. $5.00 572 $2,860.00
2411.618/08010 Architectural Color System Sq.Ft. $4.00 572 $2,288.00
TOTAL $5,148.00
Cost Distribution: Group 2 - S.A.P. 27-619-18 = 100% (Streetscaping) Hennepin County
G N 4
roup o.
Item No. Description Unit Unit Price Quantity Amount
2401.501/01143 Structural Concrete (1A43) (P) Cu.Yd. $420.00 22.9 $9,618.00
2401.501/03643 Structural Concrete 3Y43(P) Cu.Yd. $445.00 16.95 $7,542.75
2401.541/00010 Reinforcement Bars (P) Pound $1.05 664.5 $697.72
2401.541/00011 Reinforcement Bars (Epoxy Coated) (P) Pound $1.35 2589.5 $3,495.82
2411.511/00013 Structural Excavation Class U (P) Cu. Yd. $9.00 30.5 $274.50
TOTAL $21,628.79
Cost Distribution: Group 4 - S.A.P. 216-020-02 = 100% Shorewood
Total Increase of Change Order No.2
$48.405.60
SHEET 1 OF 2 SHEETS
Exhibit A
F..\WPW/M/388-0/\CHANGE C
CHANGE IN CONTRACT TTh1E
Due to this change the Contract Time:
a.
Is increased ( ) by _ Working Days
Is decreased ( ) by _ Working Days
Is increased () by _ Calendar Days
Is decreased ( ) by _ Calendar Days
b. Is not changed ( x )
c. May be revised if the work affected
the controlling operation ( )
File: CE, FE, FO, Contractor
SHEET 1 OF 2 SHEETS
~suedBy dJI /IJ~
Construction Project Engineer
Approved by:
City of Shorewood Engineer
1/6-~6
, I Date
Date
Approved By:
Hennepin County Construction Engineer
,-,-"",,~.--,~
Accepted By: ..:'c.~ ~
Contractor's Authorized Representative
Date
z. - . ..
Y b / ()6
Date
F., WP WlM I 388-0!\CHANGE ORDERSIChange Ord" Edoe