06-074
CITY OF SHOREWOOD
RESOLUTION NO. 06- 074
A RESOLUTION APPROVING A CHANGE ORDER 1
FOR THE WEDGEWOOD DRIVE, TEAL CIRCLE, AND MALLARD LANE
IMPROVEMENTS AND APPURTENANT WORK,
CITY PROJECT NO. 02-02
WHEREAS, on July 24, 2006, the City of Shorewood entered into a contract for
construction with Northwest Asphalt, Inc. for the Wedgewood Drive, Teal Circle, and
Mallard Lane Improvements and Appurtenant Work, City Project No. 02-02; and
WHEREAS, WSB and Associates has prepared Change Order 1 attached hereto
as Exhibit A, for additional work outside of the original contract; and
WHEREAS, the Director of Public Works has reviewed said Change Order and
found it to be cost effective for the project.
NOW, THEREFORE BE IT RESOLVED by the City of Shorewood to approve
Change Order Number 1 with Northwest Asphalt, Inc., that incorporates services outlined
in Change Order 1, attached hereto as Exhibit A.
ADOPTED by the City Council of the City of Shorewood this 25th day of
September, 2006.
(2/
j
)
W
ATTEST:
WOODY LOVE, MAYOR
N, ITY ADMINISTRATOR/CLERK
WEDGEWOOD DRIVE, TEAL CIRCLE, AND MALLARD LANE
IMPROVEMENTS AND APPURTENANT WORK
CITY OF SHOREWOOD, MN
WSB PROJECT NO. 1074-73
SEPTEMBER 25, 2006
OWNER:
CONTRACTOR:
CITY OF SHOREWOOD
5755 COUNTRY CLUB ROAD
SHOREWOOD, MN 55331
NORTHWEST ASPHALT, INC.
1451 STAGECOACH ROAD
SHAKOPEE, MN 55379
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
CONTRACT QUANTITIES ARE MODIFIED AS SHOWN ON THE ATTACHED DETAIL.
Storm Sewer Revisions
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR FORM
ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS: N/A
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER:
NET INCREASE OF THIS CHANGE ORDER:
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS:
$1,053,041.82
$0.00
$1,053,041.82
$17,947.60
$1,070,989.42
ORIGINAL COMPLETION DATE (SUBSTANTIAL): 10/27/2006
NET CHANGE FROM PREVIOUS CHANGE ORDERS: NONE
COMPLETION DATE PRIOR TO THIS CHANGE ORDER: 10/27/2006
NET INCREASE OF CHANGE ORDER: NONE
COMPLETION DATE WITH APPROVED CHANGE ORDER~ 10/27/2006
RECOMMENDED BY:
ER
APPROVED BY:
~. ~~~NATURE
WSB & ASSOCIATES, INC.
ENGINEER
NORTHWEST ASPHALT
CONTRACTOR
~...~/5-~
(. PUBLIC WORKS DIRECTOR, CI Y OF SHOREWOOD
.27.0~
DATE
WEDGEWOOD DRIVE, TEAL CIRCLE, AND MALLARD LANE September 25, 2006
IMPROVEMENTS AND APPURTENANT WORK
CITY OF SHOREWOOD, MN
WSB PROJECT NO. 1074-73
ADDED ITEMS
Item No. Mat. No. Description Qty Unit Price Extended Amount
63 2501.525 44" SPAN RC PIPE-ARCH APRON WITH T.G. AND 2 EACH $4,286.00 $8,572.00
SHEETPILED END SECTION
64 2503.521 44" SPAN RC PIPE SEWER DESIGN 3006 CLASS IIA 201 LI N FT $97.00 $19,497.00
65 2506.501 CONSTRUCT DRAINAGE STRUCTURE DESIGN 72- 19.2 L1N FT $587.00 $11,270.40
4020
TOTAL ADDED ITEMS CHANGE ORDER NO.1 $39,339.40
DELETED ITEMS
Item No. Mat. No. Description Qty Unit Price Extended Amount
66 2501.525 28" SPAN RC PIPE-ARCH APRON WITH T.G. AND -1 EACH $2,435.00 ($2,435.00)
SHEETPILED END SECTION
67 2501.602 24" RC PIPE APRON WI PILING -1 EACH $1,850.00 ($1,850.00)
68 2503.521 28" SPAN RC PIPE-ARCH SEWER CLASS IIA -165 L1N FT $65.00 ($10,725.00)
69 2503.541 24" RC PIPE SEWER DESIGN 3006 CLASS III -35 L1N FT $45.00 ($1,575.00)
70 2506.501 CONSTRUCT DRAINAGE STRUCTURE DESIGN 84- -7.88 L1N FT $610.00 -$4,806.80
4020
TOTAL DELETED ITEMS CHANGE ORDER NO.1 ($21,391.80)
TOTAL ADJUSTMENT TO ORIGINAL CONTRACT AMOUNT $17,947.60
Page 1