06-078
CITY OF SHOREWOOD
RESOLUTION NO. 06- 078
A RESOLUTION APPROVING A CHANGE ORDER 2
FOR THE WEDGEWOOD DRIVE, TEAL CIRCLE, AND MALLARD LANE
IMPROVEMENTS AND APPURTENANT WORK,
CITY PROJECT NO. 02-02
WHEREAS, on July 24, 2006, the City of Shorewood entered into a contract for
construction with Northwest Asphalt, Inc. for the Wedgewood Drive, Teal Circle, and
Mallard Lane Improvements and Appurtenant Work, City Project No. 02-02; and
WHEREAS, WSB and Associates has prepared Change Order 2 attached hereto
as Exhibit A, for additional work outside of the original contract; and
WHEREAS, the Director of Public Works has reviewed said Change Order and
found it to be cost effective for the project.
NOW, THEREFORE BE IT RESOLVED by the City of Shorewood to approve
Change Order Number 1 with Northwest Asphalt, Inc., that incorporates services outlined
in Change Order 2, attached hereto as Exhibit A.
2006.
ADOPTED by the City Council of the City of Shorewood this 9th day of October,
,
{L
ATTEST:
WOODY LOVE, MAYOR
, C TY ADMINISTRATOR/CLERK
WEDGEWOOD DRIVE, TEAL CIRCLE, AND MALLARD LANE
IMPROVEMENTS AND APPURTENANT WORK
CITY OF SHOREWOOD, MN
WSB PROJECT NO. 1074-73
OCTOBER 3, 2006
OWNER:
CONTRACTOR:
CITY OF SHOREWOOD
5755 COUNTRY CLUB ROAD
SHOREWOOD, MN 55331
NORTHWEST ASPHALT, INC.
1451 STAGECOACH ROAD
SHAKOPEE, MN 55379
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
CONTRACT QUANTITIES ARE MODIFIED AS SHOWN ON THE ATTACHED DETAIL.
Install portion of 8" watermain using directional drilling methods
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR FORM
ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS: 1
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER:
NET INCREASE OF THIS CHANGE ORDER:
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS:
$1,053,041.82
$17,947.60
$1,070,989.42
$39,940.50
$1,110,929.92
ORIGINAL COMPLETION DATE (SUBSTANTIAL): 10/27/2006
NET CHANGE FROM PREVIOUS CHANGE ORDERS: NONE
COMPLETION DATE PRIOR TO THIS CHANGE ORDER: 10/27/2006
NET INCREASE OF CHANGE ORDER: NONE
COMPLETION DATE WITH APPROVED CHANGE ORDER~ 10/27/2006
ER
APPR.~.. ,.770V :' __,
U- (fl/~ ;/.~v
CONTRACTOR SIGNATURE
RECOMMENDED BY:
WSB & ASSOCIATES, INC.
ENGINEER
NORTHWEST ASPHALT
CONTRACTOR
/0 'If,OCt>
DATE
WEDGEWOOD DRIVE, TEAL CIRCLE, AND MALLARD LANE
IMPROVEMENTS AND APPURTENANT WORK
CITY OF SHOREWOOD, MN
WSB PROJECT NO. 1074-73
October 3, 2006
ADDED ITEMS
Item No. Mat. No. Description
Qty
Unit
Price Extended Amount
$65.20 $68,460.00
$175.50 $1,930.50
$70,390.50
Price Extended Amount
$29.00 ($30,450.00)
($30,450.00)
$39,940.50
71
72
2504.603 DIRECTIONAL BORE 8" WATERMAIN
2504.602 SADDLE FOR CORP. STOP
1050
11
UN FT
EACH
TOTAL ADDED ITEMS CHANGE ORDER NO.2
DELETED ITEMS
Item No. Mat. No. Description
Qty
Unit
73
2504.603 8" WATER MAIN - DUCT IRON CL 52
-1 050
UN FT
TOTAL DELETED ITEMS CHANGE ORDER NO.2
TOTAL ADJUSTMENT TO ORIGINAL CONTRACT AMOUNT