06-079
CITY OF SHOREWOOD
RESOLUTION NO. 06- 079
A RESOLUTION APPROVING CHANGE ORDER 1
FOR THE CONNECTION OF SE WATER SYSTEM TO NE WATER SYSTEM,
CITY PROJECT NO. 05-05
WHEREAS, on May 22, 2006, the City of Shorewood entered into a contract for
construction with Minger Construction, Inc. for the Connection of SE Water System to NE Water
System, City Project No. 05-05; and
WHEREAS, WSB and Associates has prepared Change Order 1 attached hereto as
Exhibit A, for additional work outside of the original contract; and
WHEREAS, the Director of Public Works has reviewed said Change Order and found it
to be cost effective for the project.
NOW, THEREFORE BE IT RESOLVED by the City of Shorewood to approve
Change Order Number 1 with Minger Construction, Inc., that incorporates services outlined in
Change Order 1, attached hereto as Exhibit A.
ADOPTED by the City Council of the City of Shorewoo ~his 9th day of October, 2006.
c2J
ATTEST: WOODY LOVE, MAYOR
, CITY ADMINISTRATOR/CLERK
CONNECTION OF SE WATER SYSTEM TO
NE WATER SYSTEM
CITY OF SHOREWOOD, MN
WSB PROJECT NO. 1608-04
OCTOBER 9, 2006
OWNER:
CONTRACTOR:
CITY OF SHOREWOOD
5755 COUNTRY CLUB ROAD
SHOREWOOD, MN 55331
MINGER CONSTRUCTION, INC.
8470 GALPIN BLVD
CHANHASSEN MN 55317
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
CONTRACT QUANTITIES ARE MODIFIED AS SHOWN ON THE ATTACHED DETAIL.
Hydrant Revisions Revisions
Water Services Revisions
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR FORM
ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS: N/A
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER:
NET INCREASE OF THIS CHANGE ORDER:
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS:
$669,956.20 ORIGINAL COMPLETION DATE (SUBSTANTIAL): 9/15/2006
$0.00 NET CHANGE FROM PREVIOUS CHANGE ORDERS: NONE
$669,956.20 COMPLETION DATE PRIOR TO THIS CHANGE ORDER: 9/15/2006
$13,132.20 NET INCREASE OF CHANGE ORDER: NONE
$683,088.40 COMPLETION DATE WITH APPROVED CHANGE ORDER~ 9/15/2006
RECOMMENDED BY:
APPROVED BY:
RNEY, P.E., PROJECT,. AN GER
7
//.///
C}tl-J-
,.
{/I
// 'l~
. ~ //~ ...;
'" v <--1_
.NTRAC~R SIGNATURE
WSB & ASSOCIATES, INC.
ENGINEER
MINGER CONSTRUCTION, INC.
CONTRACTOR
APPR~~d-=
PUBLIC WORKS DIRECTOR, CITY OF SHOREWOOD
/0 -/1.00
DATE
CONNECTION OF SE WATER SYSTEM TO October 9, 2006
NE WATER SYSTEM
CITY OF SHOREWOOD, MN
WSB PROJECT NO. 1608-04
ADDED ITEMS
Item No. Mat. No. Description Qty Unit Price Extended Amount
43 2504.601 CUT IN EXTRA HYDRANT LUMP SUM $800.00 $800.00
44 2504.601 YARD HYDRANT MODIFICATIONS LUMP SUM $1,709.60 $1,709.60
45 2504.602 1-1/2" CORP STOP & SADDLE 14 EACH $339.00 $4,746.00
46 2504.602 1-1/2" CURB STOP & BOX 14 EACH $210.00 $2,940.00
47 2504.603 1-1/2" COPPER WATER SERVICE 466 L1N FT $31.00 $14,446.00
48 2531.501 REMOVE AND REPLACE B618 CURB & GUTTER 32 L1N FT $34.00 $1,088.00
TOTAL ADDED ITEMS CHANGE ORDER NO.1 $25,729.60
DELETED ITEMS
Item No. Mat. No. Description Qty Unit Price Extended Amount
49 2504.602 1" CORP STOP & SADDLE -14 EACH $186.50 -$2,611.00
50 2504.602 1" CURB STOP & BOX -14 EACH $127.60 -$1,786.40
51 2504.603 1" COPPER WATER SERVICE -410 L1N FT $20.00 -$8,200.00
TOTAL DELETED ITEMS CHANGE ORDER NO.1 ($12,597.40)
TOTAL ADJUSTMENT TO ORIGINAL CONTRACT AMOUNT $13,132.20
Page 1