Loading...
06-105 CITY OF SHOREWOOD RESOLUTION NO. 06- 105 A RESOLUTION APPROVING A CHANGE ORDER 3 FOR THE WEDGEWOOD DRIVE, TEAL CIRCLE, AND MALLARD LANE IMPROVEMENTS AND APPURTENANT WORK, CITY PROJECT NO. 02-02 WHEREAS, on July 24, 2006, the City of Shorewood entered into a contract for construction with Northwest Asphalt, Inc. for the Wedgewood Drive, Teal Circle, and Mallard Lane Improvements and Appurtenant Work, City Project No. 02-02; and WHEREAS, WSB and Associates has prepared Change Order 3 attached hereto as Exhibit A, for additional work outside of the original contract; and WHEREAS, the Director of Public Works has reviewed said Change Order and found it to be cost effective for the project. NOW, THEREFORE BE IT RESOLVED by the City of Shore wood to approve Change Order Number 3 with Northwest Asphalt, Inc., that incorporates services outlined in Change Order 3, attached hereto as Exhibit A. ADOPTED by the City Council of the City of Shorewood this 11 th day of December, 2006. aiL ATTEST: WOODY LOVE, MAYOR WSON, CIT ADMINISTRATOR/CLERK CHANGE ORDER NO.3 WEDGEWOOD DRIVE, TEAL CIRCLE, AND MALLARD LANE IMPROVEMENTS AND APPURTENANT WORK CITY OF SHOREWOOD, MN WSB PROJECT NO. 1074-73 DECEMBER 11, 2006 OWNER: CONTRACTOR: CITY OF SHOREWOOD 5755 COUNTRY CLUB ROAD SHOREWOOD, MN 55331 NORTHWEST ASPHALT, INC. 1451 STAGECOACH ROAD SHAKOPEE, MN 55379 YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION: Modify sanitary sewer service at 5455 / 5457 Mallard Lane to avoid conflicts with water service. Furnish and place 11/2" clear rock for roadbed stablization. CONTRACT QUANTITIES ARE MODIFIED AS SHOWN ON THE ATTACHED DETAIL. IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR FORti ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME: ORIGINAL CONTRACT PRICE: PREVIOUS CHANGE ORDERS: 1 & 2 CONTRACT PRICE PRIOR TO THIS CHANGE ORDER: NET INCREASE OF THIS CHANGE ORDER: CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS: $1,053,041.82 $57,888.10 $1,110,929.92 $24,663.99 $1,135,593.91 ORIGINAL COMPLETION DATE (SUBSTANTIAL): NET CHANGE FROM PREVIOUS CHANGE ORDERS: COMPLETION DATE PRIOR TO THIS CHANGE ORDER: NET INCREASE OF CHANGE ORDER: COMPLETION DATE WITH APPROVED CHANGE ORDER~ 10/27/2006 NONE 10/27/2006 NONE 10/27/2006 RECOMMENDED BY: APPROVED BY: CONTRACTOR SIGNATURE STEVEN G. GURNEY, PE, PROJECT MANAGER WSB & ASSOCIATES, INC. ENGINEER NORTHWEST ASPHALT CONTRACTOR DATE APPROVED BY: PUBLiC WORKS DIRECTOR, CITY OF SHOREWOOD Change Order No.3 Detail WEDGEWOOD DRIVE, TEAL CIRCLE, AND MALLARD LANE IMPROVEMENTS AND APPURTENANT WORK CITY OF SHOREWOOD, MN WSB PROJECT NO. 1074-73 December 11,2006 ADDED ITEMS Item No. Mat. No. Description Qty Unit Price Extended Amount 74 75 2504.603 MODIFICATIONS TO SANITARY SEWER SERVICE 2504.602 1 1/2" CLEAR ROCK 1 937.02 LUMP SUM TON $2,194.25 $23.98 $2,194.25 $22,469.74 TOTAL ADJUSTMENT TO ORIGINAL CONTRACT AMOUNT $24,663.99 Page 1