06-105
CITY OF SHOREWOOD
RESOLUTION NO. 06- 105
A RESOLUTION APPROVING A CHANGE ORDER 3
FOR THE WEDGEWOOD DRIVE, TEAL CIRCLE, AND MALLARD LANE
IMPROVEMENTS AND APPURTENANT WORK,
CITY PROJECT NO. 02-02
WHEREAS, on July 24, 2006, the City of Shorewood entered into a contract for
construction with Northwest Asphalt, Inc. for the Wedgewood Drive, Teal Circle, and
Mallard Lane Improvements and Appurtenant Work, City Project No. 02-02; and
WHEREAS, WSB and Associates has prepared Change Order 3 attached hereto
as Exhibit A, for additional work outside of the original contract; and
WHEREAS, the Director of Public Works has reviewed said Change Order and
found it to be cost effective for the project.
NOW, THEREFORE BE IT RESOLVED by the City of Shore wood to approve
Change Order Number 3 with Northwest Asphalt, Inc., that incorporates services outlined
in Change Order 3, attached hereto as Exhibit A.
ADOPTED by the City Council of the City of Shorewood this 11 th day of
December, 2006. aiL
ATTEST: WOODY LOVE, MAYOR
WSON, CIT ADMINISTRATOR/CLERK
CHANGE ORDER NO.3
WEDGEWOOD DRIVE, TEAL CIRCLE, AND MALLARD LANE
IMPROVEMENTS AND APPURTENANT WORK
CITY OF SHOREWOOD, MN
WSB PROJECT NO. 1074-73
DECEMBER 11, 2006
OWNER:
CONTRACTOR:
CITY OF SHOREWOOD
5755 COUNTRY CLUB ROAD
SHOREWOOD, MN 55331
NORTHWEST ASPHALT, INC.
1451 STAGECOACH ROAD
SHAKOPEE, MN 55379
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
Modify sanitary sewer service at 5455 / 5457 Mallard Lane to avoid conflicts with water service.
Furnish and place 11/2" clear rock for roadbed stablization.
CONTRACT QUANTITIES ARE MODIFIED AS SHOWN ON THE ATTACHED DETAIL.
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR FORti
ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS: 1 & 2
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER:
NET INCREASE OF THIS CHANGE ORDER:
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS:
$1,053,041.82
$57,888.10
$1,110,929.92
$24,663.99
$1,135,593.91
ORIGINAL COMPLETION DATE (SUBSTANTIAL):
NET CHANGE FROM PREVIOUS CHANGE ORDERS:
COMPLETION DATE PRIOR TO THIS CHANGE ORDER:
NET INCREASE OF CHANGE ORDER:
COMPLETION DATE WITH APPROVED CHANGE ORDER~
10/27/2006
NONE
10/27/2006
NONE
10/27/2006
RECOMMENDED BY:
APPROVED BY:
CONTRACTOR SIGNATURE
STEVEN G. GURNEY, PE, PROJECT MANAGER
WSB & ASSOCIATES, INC.
ENGINEER
NORTHWEST ASPHALT
CONTRACTOR
DATE
APPROVED BY:
PUBLiC WORKS DIRECTOR, CITY OF SHOREWOOD
Change Order No.3 Detail
WEDGEWOOD DRIVE, TEAL CIRCLE, AND MALLARD LANE
IMPROVEMENTS AND APPURTENANT WORK
CITY OF SHOREWOOD, MN
WSB PROJECT NO. 1074-73
December 11,2006
ADDED ITEMS
Item No. Mat. No. Description
Qty
Unit
Price
Extended Amount
74
75
2504.603 MODIFICATIONS TO SANITARY SEWER SERVICE
2504.602 1 1/2" CLEAR ROCK
1
937.02
LUMP SUM
TON
$2,194.25
$23.98
$2,194.25
$22,469.74
TOTAL ADJUSTMENT TO ORIGINAL CONTRACT AMOUNT
$24,663.99
Page 1