07-074CITY OF SHOREWOOD
RESOLUTION NO o7-074
A RESOLUTION ACCEPTING FINAL IMPROVEMENTS AND AUTHORIZING
FINAL PAYMENT FOR THE WEDGEWOOD DRIVE, MALLARD LANE AND
TEAL CIRCLE RECONSTRUCTION PROJECT; CITY PROJECT 02-02
WHEREAS, on July 25, 2006, the City of Shorewood entered into a contract for
construction with Northwest Asphalt, Inc. for the Wedgewood Drive, Mallard Lane and
Teal Circle Reconstruction Project, City Project #02-02; and,
WHEREAS, the Contractor has petitioned for final acceptance of the project and
final payment based on work perfornled to date; and,
WHEREAS, the Project Manager has made a final inspection of the project and
recommends acceptance and final pa}nnent be made by the City.
NOW, THEREFORE BE IT RESOLVED:
The City hereby does accept the work completed pursuant to said contract and
authorizes final payment to the Contractor, and the two-year guarantee shall
commence as of June 27, 2007.
ADOPTED by the City Council of the City of Shorewood this 26th day of
November, 2007.
ATTEST:
--~
fa ~ ~
~;,, .
~/,
Craig ~°: awson, City Administrator/Clerk
Christine Lizee, Mayor