08-007CITY OF SHOREWOOD RESOLUTION NO. 08-007 A RESOLUTION APPROVING A CHANGE ORDER 1 FOR THE REHABILITATION OF LIFT STATION #12 PROJECT, CITY PROJECT NO. 06-01 WHEREAS, on July 23, 2007, the City of Shorewood entered into a contract for construction with Engineering and Construction Innovations, Inc. for the Rehabilitation of Lift Station #12 Project, City Project No. 06-01; and WHEREAS, Engineering and Construction hnlovations, Inc has prepared Change Order 1 attached hereto as Exhibit A, for additional work outside of the original contract; and WHEREAS, the Director of Public Works has reviewed said Change Order and found it to be cost effective for the project. NOW, THEREFORE BE IT RESOLVED by the City of Shorewood to approve Change Order Number 1 with Engineering and Construction hmovations, Inc., that incorporates services outlined in Change Order 1, attached hereto as Exhibit A. ADOPTED by the City Council of the City of Shorewood this 28th day of January, 2008. ~~ ~'~` ~ L ATTEST: Kristine Lizee, Mayor 10/19/2007 15:34 IFA~ ECIINC1002@Q4VEST.NET ~ Nap 17.]001/002 Engineering & Construction ' ~~--= Innovations, (rec. nctober 1 ~, 2007 Kevin I~~c~~rm~n, PC ~'JSF3 ~~; Associates 701 Xenia ~'tvenue South -Suite 300 Mirn~eal~~olis, MN 55416 R>~: City of Shorewood Lift Station I~lumber 12 IZ~I : ~f;xtt;nded Completion Date Mr. Ne«~nan: Engineering & Co~istruction Inrun-ations (ECl} has been direr#ed by the City oi' Shorewood to delay the commencei~~ent of site activities frn~ the City of Slaore~~rood Lift Station Numl3er 12 Project until spring 2004, The put-1?ose of this correspondcnce is to address the project impacts that arc a result of this direction. iVlaterial suppliers have been contacted regarding warranty, escalation and material warehousing concerns. The pump s>.rpplicr, ElectricPump confirmed that they 4~~ill honor their warranty fi•on~ date of illstailation. The control panel supplier, Quality Flow also conlii-~ned their «~arrat~ty fi-ozn time of installation on the condition that ECI stores ilae control panel in a heated environment through the tit~inter• months. ECI ~~~ill store all lift station n~atcrials at our shop and is asking for a one hundred dollars per month «~arehol~TSing hee.. Altornativel~r, 1~.C"1 swill deli~~ea• the control panel and pumps to the city for storage fora 5250 delivery fee. The subeotltractors have also been contacted to discuss cost escalation for their services. Escalation costs resulting fi-orn the delay are as follows: 1. 1_Y;lectr•Iccrl Subcontructar...........~~'S.O0 2. Cvi~tru~, Sl~~hcoi~traclc~r ..............$50.0(1 3. 1'avin,; Strbcoiztrcrctnr• ......... ......~'16?.lI(1 ECI will incur equipment operating az~d labor escalation costs for project delays to the 2008 construction season. The labor and equipztrent escalation costs are $700 for the 20()8 construction year. The to(~al ~:xlditional cr?sts are summarized as follo~~~s: 1. ,Suhca~~tractar C'o.cts ......................... fi9_i7. ~JO 2. Starrz,,e Fc}es 7mas~i)SIO~........,... X700.00 -_.__..... ~ ....... S~. 3. Certeral C'o~ztrcrc•tor Costs ................$700.1)0 Total ........................ . ...$2,337.f10 Exhibit A 710 t3ar~~e Chancel Koad • PU Box 709 ~ St. £'aul, A•liiuiesc~t~ 5107 °t C:} .-_ ~i51-29ti-y l 1 I ~ Tt1X: h~ l -2.95-~)1 1 i • ~~~ ~~~~1~'{'S: 17i-~i~-t-1 Oh 1 10/19/2007 15:34 IFAX ECIINC1002@Q4VEST.NET -~ Nap C~7j002/002 hQr- Ae~i~irrm. Y[: Patrc 2 oft I ili I y%%20(17 Thar.~l< you for your attention to these items. 1 look fo7-~~~ard to rcceivir~g change order documentation addressing the delay costs and the revised con~hletian date. If there are any c}uestions or concerns with the above please contact me accordingly. Sincerely, Engineerir~~~ ~ Construction Innovations; lne. Nap Sec~tt Project Manager- ~:: Shane McFadden; Job files